3. A PERT project has an ending completion time of 62 weeks with a variance of 16 weeks. Determine the following probabilities: a) The project is completed in 68 weeks. b) The project takes longer than 70 weeks. c) The project is completed between 60 and 68 weeks.

Reference no: EM13335269

Questions Cloud

If someone has given for one year as a lump sum : If someone has given you $10,000 for one year as a lump sum, or $1,000 over ten intervals, or $100 over 100 intervals (always over one year) assuming a 5% APR can income be gained "continuously"?
The orbital hybridization that occurs for the central carbon : Using partial orbital diagrams show the orbital hybridization that occurs for the central carbon that can explain the formation of CH4
Show the effects of recognizing the nsf check : Show the effects of recognizing the NSF check on the financial statements by recording the appropriate amounts in a horizontal statements model
Determine at what frequency will the fuse burn out : A 56.7-µF capacitor is connected to a generator operating at a low frequency. The rms voltage of the generator is 3.88 V and is constant. at what frequency will the fuse burn out
The project is completed between 60 and 68 weeks : 3. A PERT project has an ending completion time of 62 weeks with a variance of 16 weeks. Determine the following probabilities: a) The project is completed in 68 weeks. b) The project takes longer than 70 weeks. c) The project is completed between 60..
Why do you suppose the federal government gives special : Why do you suppose the federal government gives special treatment to owners of fertile farmland rather than, say, automobile mechanics?
What minimum diameter is required for the wire : A steel wire of length 1.92m with circular cross section must stretch no more than 0.210cm, What minimum diameter is required for the wire
Explain treatment of the solution with clo : Treatment of the solution with ClO- in alkaline solution yields a yellow solution and a colored precipitate. Ions Present- Ions absent
Purchase of merchandise on credit using perpetual inventory : Which of the is allowed under generally accepted accounting principles - purchase of merchandise on credit using a perpetual inventory system includes

Reviews

Write a Review

Project Management Questions & Answers

  Describing project management

The project is moving along with the normal set-backs?nothing major, though, until today. In your regular status meeting with one of your project vendors, the account manager, George, closed your door and told you that you have a problem.

  Who calls the shots on projects

describe when the stakeholder and identification process should take place during the planning of the project

  What is the difference between negligence and strict

What is the difference between negligence and strict liability? What are some of the latest amendments to the Truth-in-Lending Act?

  The studies and techniques developed by taylor

The studies and techniques developed by Taylor and the Gilbreths simply enabled employers to get more work out of their employees

  What is the exponential smoothing forecast value

what is the exponential smoothing forecast value for the following period?

  What is the projected revenue and costs

What is the projected revenue, costs, and potential profits would be over the next 10 years based on the current capacity,

  Compute the optimal order quantity of dvd players

Compute the optimal order quantity of DVD players. Determine the appropriate reoder point (in units). Compute cost savings that the company will realize if it implements the optimal inventory procurement decision.

  Calculating annual holding cost rate

Calculate the annual holding cost rate for FFF?

  Explain the disruptive force and organizations response

Examine a change you experienced that was initiated by a disruptive force and explain the disruptive force and the organization's response to meet the challenge.

  Assembly line balancing

Historical employee efficiency rates and balance delay rate

  Different categories of consumer products

What are the four different categories of consumer products and how could you promote each category and motivate consumer interests? Your response should be at least 200 words in length.

  Importance of incorporating a budget into project schedule

Explain the importance of incorporating a budget into a project schedule.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd