Reference no: EM13230751
SerDoc is a company that manufactures customised medical equipment for hospitals and is about to initiate a project for building a new machine for a recent order from a hospital. The project involves the following six phases: initiating, requirements gathering, design, development and testing, documentation, deployment and testing. The project is scheduled to start on 15 October.
The duration and precedence relationships (or sequencing) between the tasks of the project are provided in the table below:
|
Phase
|
Task Name
|
Task ID
|
Immediate Predecessor
|
Time (Days)
|
|
Initiating
|
Defining the scope of the project
|
1
|
|
5
|
|
Initiating
|
Analysing the existing product which is being produced by SerDoc
|
2
|
|
10
|
|
Requirements Gathering
|
Preparing the requirements document and a high-level design
|
3
|
1, 2
|
15
|
|
Requirements Gathering
|
Conducting a proof of concept to validate the approach
|
4
|
3
|
7
|
|
Requirements Gathering
|
Signoff of requirements and a high-level design from the customers who have ordered the machine
|
5
|
3
|
4
|
|
Design
|
Design of hardware components
|
6
|
5, 4
|
20
|
|
Design
|
Detailed product specifications
|
7
|
5
|
30
|
|
Design
|
Detailed program design*
|
8
|
7
|
20
|
|
Development and Testing
|
Manufacturing of the shell of the machine
|
9
|
7, 8
|
40
|
|
Development and Testing
|
Assembling of the electronic components of the machine
|
10
|
7
|
10
|
|
Development and Testing
|
Testing of the circuit for accuracy of responses
|
11
|
9, 10
|
40
|
|
Development and Testing
|
Testing of the manufactured machine and calibration to standards
|
12
|
11
|
15
|
|
Documentation
|
Preparing an installation and user manual
|
13
|
Finishes with 8, 12
|
30
|
|
Deployment and Testing
|
Installation of the machine at the hospital
|
14
|
12
|
5
|
|
Deployment and Testing
|
Conducting trials and checking all functionality at the hospital after installation
|
15
|
12, 14
|
10
|
|
Deployment and Testing
|
Getting client signoff
|
16
|
13, 15
|
0
|
|
Deployment and Testing
|
Training hospital technicians for using the machine
|
17
|
12
|
15
|
|
Deployment and Testing
|
Commissioning of the machine at the hospital
|
18
|
8
|
9
|
Part
On the basis of the above information, use Microsoft Project to create a project plan that lists project tasks, establishes precedence relationships between tasks, sets precedence relationships, calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and deployment and testing.
What is the end date of the project?
|
Describe the additional factors that impact global supply
: Based on the concept of globalization, many businesses operate and compete in a global environment. Describe the additional factors that affect/impact global supply chains.
|
|
Explain the genetic variation
: How would the research programs of the two schools have influenced their perceptions about the amount of genetic variation present in the wild?
|
|
Estimate the electron and hole drift velocity
: Consider an n-Si with doping of 9*10^16cm^-3. In a certain region of this sample, there is an electric field of 1000V/cm. Estimate the electron and hole drift velocity and the total drift current density in that region.
|
|
What is the maximum possible output per week for this line
: An assembly line with 7 tasks is to be balanced. The longest task is 8 minutes, the shortest task is 2 minutes, and the sum of the task times is 53 minutes. The line will operate for 6 hours per shift, 1 shifts per day, 6 days per week.
|
|
The project duration and identifies the critical path
: Calculates the project duration, and identifies the critical path. While preparing the project plan, categorise the project tasks in the different phases of initiating, requirements gathering, design, development and testing, documentation, and de..
|
|
Compute the molar mass of the unknown gas
: Calculate the molar mass of the unknown gas. Remember that the faster the rate of effusion, the shorter the time required for effusion; that is, rate and time are inversely proportional.
|
|
Compute the equilibrium carrier concentrations
: Compute the equilibrium carrier concentrations and the position of the Fermi level with respect to the conduction band edge for a uniformly doped Si region with N_D=1*10^16 cm^-3 and N_A = 1*10^17 cm^-3 at room temperature.
|
|
What is the minimum sales quantity that would justify
: What is the minimum sales quantity that would justify the purchase of new equipment?
|
|
State standardized against a standard solution of hcl
: If 1L of .15M NaOH is unprotected from mmol of CO2, what will be its new molarity when it is standardized agains a standard solution of HCl using
|