Complete the network diagram, do the necessary calculations, and state the critical path(s) and the project completion time. State the critical path(s) and the completion time as, for example, "A - B - C @ 20", meaning Activities A, B, and C comprise the critical path and the completion time is 20 time units.
Complete each problem, clearly stating the assignments made (i.e., in the format A-->2, etc.), the total assignment cost and any special considerations (e.g. multiple optimal assignments, tasks remaining undone, etc.).
The possible assignments of machinists to machines is shown below. What is the assignment that will optimize total assignment cost? What is that cost?
Machine--> 1 2 3 4 5
Machinist
A 8 10 10 15 2
B 14 21 17 10 2
C 14 18 22 25 3
D 16 19 20 24 2
E 8 11 11 10 2