A project manager for a large manufacturing company is working on a project that calls for a new building to be constructed to house a new clean system manufacturing process that is critical to the success of the project. Construction is not a core competency of his company. His team has the ability to create a detailed SOW with liquidated damages in the event that specific deliverables are delivered on time. The PM is in the Plan Procurements phase of the project, and needs to select a contract type for this work. Which of the following is the best type of contract for this situation?
a. FP (Fixed price)
b. CPFF (Cost plus fixed fee)
c. CPIF (Cost plus incentive fee)
d. T&M (Time and materials)
Note: Please explain supporting rationale for answer selected
Which of the following best defines the "congruence" model of diagnosing change? Includes purpose, structure, rewards, and helpful mechanisms.
deliverable length 1000-1200 wordsresearch a real product and explain how it is a product of denationalization
(1) Define the term, transfer of learning. (2) A critical issue in training is the transfer of training, and ethics training is no exception. How could the transfer of ethics training back to the workplace be maximized?
You expect the selling price to average $.05. a) What is the break-even point in dollars? b) What is the break-even point in units?
You have been chosen to create an e-commerce program to the board of directors. Present your argument on why senior management should buy into your e-commerce program.
At this point we know the following about male and female salaries. Male and female overall average salaries are not equal in the population.
Who gained the benefit by keeping the passengers on the airplane?
Solve the following linear program using the decomposition principle: minimize z = ?2x1 ? 5x2 subject to x1 + 2x2 = 13.5 x1 + 3x2 = 18.0 x1 ? 9 x2 ? 5 x1, x2 ? 0.
you are responsible for an operation that has 12 distinct jobs. seven of those jobs must be processed in two
peters paper clips uses a three-stage production process cutting wire to prescribed lengths inner bending and outer
Discuss whether too much governmental regulation of business or too little governmental regulation of business presents the greater danger to:
Compare the best plans in the JC Company and the Tucson Parks and Recreation Department. What do they have in common?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd