1. Essentially, the output of aggregate planning indicates
A. the materials required for the business plan. B. the operations capacity. C. the rough-cut capacity for the long term. D. the quantity and timing of planned production. E. the forecast of aggregate demand.
2. Priority rules are often used for scheduling in a/an:
A. assembly-line process. B. fixed-position layout environment. C. job shop. D. continuous flow process. E. product layout environment.
3. If a company is producing a good below the break-even point, it is absorbing a net loss on the product.
True or False
4. Studies on a bottle-filling machine indicate it fills bottles to a mean of 16 ounces with a standard deviation of 0.10 ounces. What is the process specification, assuming the Cpk index of 1?
A. lower spec = 0.1 ounces and upper spec = 1 ounce
B. lower spec = 15.1 ounces and upper spec = 16.9 ounces
C. lower spec = 12.0 ounces and upper spec = 21.4 ounces
D. lower spec = 14.3 ounces and upper spec = 17.7 ounces
E. lower spec = 15.7 ounces and upper spec = 16.3 ounces