1. The aggregate plan is a long-term plan?
A. True
B. False
2. The best way to select the location of capacity of non-materials resources to conduct the aggregate plan is to find the lowest cost.
A. True
B. False
3. A capacity plan based on actual performance is better than one based on theoretical performance.
A. True
B. False
4. Which is NOT part of capacity requirements planning (CRP) within the aggregate supply chain plan often referred to as manufacturing resource planning or MRPII.
A. amount of capacity needed
B. timing of output
C. sales forecast
D. balance in the system
E. flexibility of the response
5. Strategic capacity planning insures that supply chain operations will always have adequate, non-materials resources to produce it's output.
A. True
B. False
6. Aggregate plans must have valid and accurate forecasts.
A. True
B. False
7. What aggregate plan for uneven demand tries to vary the output by changing schedules and work forces frequently to meet forecasted demand?
A. chase strategy
B. level strategy
C. high employment strategy
D. make-to-stock strategy
E. make-to-order strategy
8. Which is NOT one of the methods to determine the potential capacity of a process?
A. best operating procedure
B. determination by study
C. demonstrated by performance
D. daily scheduling of capacityQuestion 10
9. The 'production plan' in supply chain management is known as what?
A. supply chain management
B. sales & operations planning
C. strategic planning
D. aggregate plan
E. financial planning
10. Which is NOT a suggested participant on the RCA team to find problems with processes and their causes?
A. top management
B. process owners & managers
C. customers
D. accounting personnel
E. customer service & sales personnel