The important location factors and ratings

Assignment Help Project Management
Reference no: EM13668200

Arsenal Electronics is going to construct a new $1.2 billion semiconductor plant and has selected four towns in the Midwest as potential sites. The important location factors and ratings for each town are as follows:


View complete question »

Location Factor

Weight

Scores (0 to 100)

Abbeton

Bayside

Cane Creek

Dunnville

Work ethics

0.18

80

90

70

75

Quality of life

0.16

75

85

95

90

Labor laws/unionization

0.12

90

60

60

70

Infrastructure

0.10

60

50

60

70

Education

0.0

 

Reference no: EM13668200

Questions Cloud

Explain what the percent potassium chlorate : If 789mL of gas is collected over water is collected over water at .976 atmospheres and 30.0 C, explain what the percent potassium chlorate is in the original mixture? Vapor pressure of water is at 30.0 C = .023 atm.
Was the sample size adequate : Was the sample size adequate?
State balance equations for all substitution reactions : State balance equations for all substitution reactions between the alkyl halides and NaI (sodium iodide)
Explain reactions indicate which substance is oxidized : For each of the following reactions indicate which substance is oxidized and which reduced. Which substance is the oxidizing agent and which is the reducing agent
The important location factors and ratings : The important location factors and ratings
Compute the equilibrium constant kc : 3.88 mol of A as well as 4.11 mol of B are placed in a 0.640 L container. Compute the equilibrium constant Kc given that 1.63mol of C was present at equilibrium.
Depict the structures of all alkenyal side products : Depict the structures of all alkenyal side products that could be formed by dehydration of 1- methyl-2-butanol by an e1 mechanism
The important location factors and ratings : The important location factors and ratings
Compute the partition coefficient for the compound : This aqueous solution is extracted with 5.0mL of hexane. Separation as well as analysis of the aqueous phase shows that it now contains 12mg of the organic compound. Compute the partition coefficient for the compound.

Reviews

Write a Review

Project Management Questions & Answers

  Important information about need help with project

important information about need help with project belowresearch the visa website. after reviewing of all the documents

  Phase 1 planning 1 select a name for the company2 determine

phase 1 planning 1. select a name for the company.2. determine the short-term goals of the company.3. determine the

  Find the cost benefits analysis

Explain how do you ensure that the requirements are fully developed and vetted by project SMEs so that the risk of a scope increase is low?

  Purpose of analyzing the risk of a decision

Purpose of analyzing the risk of a decision - Explain what is the purpose of analyzing the risk of a decision

  Leadership and skills planning and control there are many

there are many projects known to the public which have received attention by the media because of their perceived

  What approach do you use for project identification

What approach do you use for project identification?

  Negotiating project workpeople handle conflict in different

negotiating project workpeople handle conflict in different ways. assume you are the project leader and two of your

  Calculate the expected time and variance of each activity

Calculate the expected time and variance of each activity and draw a network diagram and identify critical path and project completion time?

  What types of risks are inherent in a project

Project Management Risks - What types of risks are inherent in a project

  Evaluating potential projects before implementing it

Why do you think it is important to evaluate potential projects before proceeding with implementation?

  Calculate the return on equity

Determine whether a steel company or a retail food chain would have a greater business risk and calculate the return on equity (ROE) for 2010 and 2014, using all of the five components.

  Project management and how to write a proposalexplain a

project management and how to write a proposalexplain a work related situation you feel you could be improved. for

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd