The high-protein energy smoothie project

Assignment Help Financial Management
Reference no: EM132047212

Quantitative Problem: Sunshine Smoothies Company (SSC) manufactures and distributes smoothies. SSC is considering the development of a new line of high-protein energy smoothies. SSC's CFO has collected the following information regarding the proposed project, which is expected to last 3 years:

The project can be operated at the company's Charleston plant, which is currently vacant.

The project will require that the company spend $4.9 million today (t = 0) to purchase additional equipment. For tax purposes the equipment will be depreciated on a straight-line basis over 5 years. Thus, the firm's annual depreciation expense is $4,900,000/5 = $980,000. The company plans to use the equipment for all 3 years of the project. At t = 3 (which is the project's last year of operation), the equipment is expected to be sold for $2,300,000 before taxes.

The project will require an increase in net operating working capital of $700,000 at t = 0. The cost of the working capital will be fully recovered at t = 3 (which is the project's last year of operation).

Expected high-protein energy smoothie sales are as follows:

Year                       Sales

1                          $2,400,000

2                           7,850,000

3                           3,500,000

The project's annual operating costs (excluding depreciation) are expected to be 60% of sales.

The company's tax rate is 40%.

The company is extremely profitable; so if any losses are incurred from the high-protein energy smoothie project they can be used to partially offset taxes paid on the company's other projects. (That is, assume that if there are any tax credits related to this project they can be used in the year they occur.)

The project has a WACC = 10.0%.

What is the project's expected NPV and IRR? Round your answers to 2 decimal places. Do not round your intermediate calculations.

NPV $

IRR %

Reference no: EM132047212

Questions Cloud

The total market value of the company outstanding debt : The bonds make semiannual payments. What is the total market value of the company’s outstanding debt?
Net present value method and present value index : Analysis for a service company Continental Railroad Company is evaluating three capital investment proposals by using the net present value method.
How company can use swap to convert the debt to fixed rate : Indicate how the company can use a swap to convert the debt to a fixed rate.
Determine when the company should replace the machine : Determine when the company should replace the machine. Determine the AW for the next 3 years.
The high-protein energy smoothie project : If any losses are incurred from the high-protein energy smoothie project they can be used to partially offset taxes paid on the company's other projects.
Call-put options on t-bonds to generate positive cash flows : What are two ways in which the institution can use call and put options on T-bonds to generate positive cash flows if this situation were to occur?
Component cost of debt and component cost of preferred stock : Calculate firm’s component cost of debt and component cost of preferred stock. Hashem Inc. is considering single project this capital budgeting period,
What will be the total benefit for the existing shareholders : What will be the total benefit for the existing shareholders of Jael? What about the existing shareholders of Sisera?
Calculate the expected return on this portfolio : Calculate the expected return on this portfolio.

Reviews

Write a Review

Financial Management Questions & Answers

  Identify the appropriate policy provision that applies

The waiver-of-premium rider and guaranteed purchase option are attached to the policy. Identify the appropriate policy provision that applies.

  Find the rate of interest payable on the savings account

At the beginning of each year for 10 years, e4,800 is deposited in a savings account which pays a certain fixed rate of interest per annum. At the time of the last payment, the proceeds of the account are used to purchase a level annuity payable annu..

  Recalculate original npv and irr using these new estimates

Using your cost of capital estimates in part 5, recalculate the original NPV and IRR using these new estimates.

  Players expect constant-rising or falling exchange rate

The Mexican government pegged the Mexican peso exchange rate to the dollar. do market players expect a constant, rising or falling exchange rate?

  Firm desires to finance new projects

If a firm desires to finance new projects with 65% retained earnings and 35% debt, what is its weighted average cost of capital (WACC) if its equity’s required rate of return is 14% and its new debt issues are expected to yield 6.5%. The corporation’..

  What is the correlation between the two securities

Suppose you own a two-security portfolio. You have 54% of your money invested in Security X and the remainder in Security Y. The standard deviations of Securities X and Y are 30 percent and 25 percent. What is the correlation between the two securiti..

  What is the 1-year interest rate expected one year

If the unbiased expectations theory of the term structure of interest rates holds, what is the 1-year interest rate expected one year from now, E(2r1)?

  Determine the amount of each lease payment

Determine the amount of each lease payment and Record appropriate journal entries

  Determine? the current mortgage payment

determine? the current mortgage payment?, the total interest? paid, the payment after the first adjustment.

  If the winners prize increases at same rate what will be in

In 1895, the first Putting Green Championship was held. The winner's prize money was $210. In 2010, the winner's check was $1, 410,000.

  Value of each warrant attached to the bond issue

If investors pay $700 for each bond, what is the value of each warrant attached to the bond issue?

  When estimating the cost of debt to use in the wacc

When estimating the cost of debt to use in the WACC, which of the following types of debt should be included?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd