The good homes construction

Assignment Help Management Theories
Reference no: EM131100441

Reconsider Prob. 10.5-4 involving the Good Homes Construction Co. project to construct a large new home. Michael Dean now has generated the plan for how to crash this project (as given as an answer in the back of the book). Since this plan causes all three paths through the project network to be critical paths, the earliest start time for each activity also is its latest start time. Michael has decided to use PERT/Cost to schedule and control project costs.

(a) Find the earliest start time for each activity and the earliest finish time for the completion of the project.

(b) Construct a table like Table 10.10 to show the budget for this project.

(c) Construct a table like Fig. 10.15 (by hand) to show the schedule of costs based on earliest times for each of the 8 weeks of the project.

(d) Now use the corresponding Excel template in your OR Courseware to do parts (b) and (c) on a single spreadsheet.

(e) After 4 weeks, activity A has been completed (with an actual cost of $65,000), and activity B has just now been completed (with an actual cost of $55,000), but activity C is just 33 percent completed (with an actual cost to date of $44,000). Construct a PERT/Cost report after week 4. Where should Michael concentrate his efforts to improve cost performances?

Prob. 10.5-4

Good Homes Construction Company is about to begin the construction of a large new home. The company's President, Michael Dean, is currently planning the schedule for this project. Michael has identified the five major activities (labeled A, B, . . . , E) that will need to be performed according to the following project network.

He also has gathered the following data about the normal point and crash point for each of these activities.

These costs reflect the company's direct costs for the material, equipment, and direct labor required to perform the activities. In addition, the company incurs indirect project costs such as supervision and other customary overhead costs, interest charges for capital tied up, and so forth. Michael estimates that these indirect costs run $5,000 per week. He wants to minimize the overall cost of the project. Therefore, to save some of these indirect costs, Michael concludes that he should shorten the project by doing some crashing to the extent that the crashing cost for each additional week saved is less than $5,000.

(a) To prepare for analyzing the effect of crashing, find the earliest times, latest times, and slack for each activity when they are done in the normal way. Also identify the corresponding critical path(s) and project duration.

(b) Use marginal cost analysis to determine which activities should be crashed and by how much to minimize the overall cost of the project. Under this plan, what is the duration and cost of each activity? How much money is saved by doing this crashing?

(c) Now use the linear programming approach to do part (b) by shortening the deadline 1 week at a time from the project duration found in part (a).

Reference no: EM131100441

Questions Cloud

Prepare a report to be distributed internally to department : Prepare a 2- to 3-page report to be distributed internally to department employees on "Centervale Policing, a Community-Based Approach."
Civilization broadcasting a signal : Consider a civilization broadcasting a signal with a power of 1.4×104 watts. The Arecibo radio telescope, which is about 300 meters in diameter, could detect this signal if it is coming from as far away as 118 light-years. Suppose instead that the..
Show why the overall code is uniquely decodable : By considering a string of 1020 binary symbols into the encoder, show that the number of occurrences of b per input symbol is, with very high probability, very close to 0.1. (d) Combine parts (b) and (c) to find L, the expected number of output bi..
Pairs of jeans to the cost of the jeans : Look at the table that reprecents the local store (1 pair or jean $24 ,2 pair of jean $48 , 3 pair of jean $72 ) for each row in the table , find the ratio of the number of pairs of jeans to the cost of the jeans.
The good homes construction : Reconsider Prob. 10.5-4 involving the Good Homes Construction Co. project to construct a large new home. Michael Dean now has generated the plan for how to crash this project (as given as an answer in the back of the book).
Expected profit per warranty : If the store charges $15 for the extended warranty, what will their expected profit per warranty be? If the company sells 100,000 projectors and 15% of the customers purchase the extended warranty, what will their expected profits from extended wa..
Obtaining future contracts for defense work : Reconsider the Lockhead Aircraft Co. problem presented in Prob. 10.4-6 regarding a project to develop a new fighter airplane for the U.S. Air Force. Management is extremely concerned that current plans for this project have a substantial likelihoo..
Develop your internet and library research skills : Develop your Internet and library research skills. Evaluate your topic from the perspective of different cultures and/or political viewpoints as well as your own. Improve personal and social responsibility.
Find the pmf of d2 : Find the pmf of D2. One point of this exercise is to convince you that Dn is a useful rv for proving theorems, but not an rv that is useful for detailed computation. It also shows clearly that Dn can depend on more than the first n source letters.

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd