The following activities are part of a project to be

Assignment Help Project Management
Reference no: EM13363061

The following activities are part of a project to be scheduled using CPM:

Activity Intermediate Predecessor Time (WEEKS)
A 6
B A 3
C A 7
D C 2
E B,D 4
F D 3
G E,F 7

a. Draw the network.

b. What is the critical path?

c. How many weeks will lit take to complete be project?

d. How much slack does the activity B has?

Reference no: EM13363061

Questions Cloud

Tying in resources to projectssome companies choose not to : tying in resources to projectssome companies choose not to tie resources to their projects. in what ways does this
Aligning a project with business goalsyou know you need to : aligning a project with business goalsyou know you need to ensure that this project is aligned with business goals.
Calculating annual project free cash flowin the spring of : calculating annual project free cash flowin the spring of 2010 jemison electric was considering an investment in a new
Extimate project effortcosts such as salaries and equipment : extimate project effortcosts such as salaries and equipment rental are a more cut and dry expenses to estimate than the
The following activities are part of a project to be : the following activities are part of a project to be scheduled using cpmactivity intermediate predecessor time weeksa
Project charter importanceexplain the importance of a : project charter importanceexplain the importance of a project charter to the project manager. how does a strong project
Project management plan and phasesshow three important : project management plan and phasesshow three important items that belong within a project management plan and the
Managing project trade-offswhen managing project trade-offs : managing project trade-offswhen managing project trade-offs it is important to understand the root cause of the
Change continually happens during a project as you learn : change continually happens during a project as you learn more information and make adjustments. some changes have small

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd