5) The marketing department at Bodnar Industries is developing a promotional campaign to introduce a new product. A listing of the various activities required, their immediate predecessors, and estimates of their times (in days) is given below.
a) Draw the precedence diagram for this network.
b) Identify the critical path and the expected project completion time.
c) Calculate the expected slack time for each activity. Also compute the slack time for each path relative to the critical path completion time.
d) What is the probability that the critical path will be completed in more than 65 days?
e) How many days should the marketing manager allow for completion of the critical path if he wants to be 99% sure that the critical path will be completed within this allowed time?
Activity
Description
Immediate Predecessors
Optimistic Time
Most Likely Time
Pessimistic Time
A
Rough brochure layout
--
2
3
5
B
Review brochure
6
8
10
C
Final brochure layout
4
D
Final brochure artwork
7
11
E
Design display
12
15
20
F
Rough display artwork
G
Review display
H
Revise display
I
Final display artwork
F,H
1
J
Make display plates
18
23
26
K
Make brochure plates
D,I
13
16
L
Make and ship displays
14
M
Print and ship brochures
Frank Hurley is the farmer with 250 acres on which he wishes to plant wheat and corn to maximize his expected return for season. Based upon the output, what key points would you recommend to Frank?
You are looking to start your own business and you have settled on opening a Pizza take-out restaurant. How do you begin process of researching your new endeavor?
Process Layout, Product Layout, Fixed position Layout, shaping of business policy, key objective of the operations manager, managing both demand and capacity
Minimal-spanning tree technique and Shortest-route technique
This solution discussed the similarities and differences between operations and supply chain management. You have been asked to develop a short presentation on comparing and contrasting operations management to supply chain management.
Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.
Explain the elements of valid contract, and describe how consumers and banks each have a duty of good faith and fair dealing in the banking relationship.
The solution discusses an ethical problem in workplace environment and solutions to solve the problem by using the Ethical Decision Model is as well explained. Also discussed is an opinion on how employee compensation should be determined based on..
Ccompare the effectiveness of different leadership styles in different organizations
This solution states the usefulness of surveys in determining the reason for high turnover rates in organization.
Provide at least 200 word answer to: Jacques Pierre manufactures and sells a line of perfume - Le Peux - in distinctly-shaped containers that are instantly recognizable. May Jacques Pierre register the shape of the containers as a trademark?
Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd