The critical path in a project network represents the:
A) Shortest duration path through the network
B) Longest duration path through the network
C) Most important tasks on a project
D) Network path using the most resources
E) Highest-risk tasks on a project
Activities which can take place at the same time are termed:
A) Parallel activity
B) Critical path
C) Burst activity
D) Merge activity
E) Independent activity
The forward pass in project network calculations determines the:
A) Earliest time's activities can begin
B) Earliest time's activities can be finished
C) Duration of the project
D) Both A and B are correct
E) A, B, and C are all correct
The backward pass in project network calculations determines the:
A) Latest time's activities can begin
B) Earliest time's activities can be finished
C) Critical path
D) Both A and C are correct
E) A, B, and C are all correct
The amount of time an activity can be delayed and yet not delay the project is termed:
A) Total slack
B) Free slack
C) Critical float
D) Float pad
E) Slip pad
True about work packages
: All of the following are true about work packages except: The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers.
|
Appear on a project scope checklist
: The lowest element in the hierarchical breakdown of the WBS is: "To construct a high-quality, custom home within five months at costs not to exceed $150,000" is best classified as: Which of the following is not one of the items that would appear on a..
|
Example of an organizational process asset
: Which one of the following is not an example of an Organizational Process Asset? The first step in creating the necessary information to manage a project is to: In Microsoft Project, if a resource is scheduled for more work - in a given time period -..
|
Calculate the total slack in an activity
: Which of the following will correctly calculate the total slack in an activity? If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first? Nodes on an AON project n..
|
The critical path in a project network represents
: The critical path in a project network represents the: Activities which can take place at the same time are termed: The backward pass in project network calculations determines the: The amount of time an activity can be delayed and yet not delay the ..
|
Bottom-up approaches for estimating project times and costs
: Which of the following are not bottom-up approaches for estimating project times and costs? Which of the following is not one of the recommended guidelines for developing useful work package estimates? Reasons why estimating time and cost are importa..
|
Quality of estimates for project times and costs
: Which of the following is provided by a project network but not by the work breakdown structure? On a project network, the activity times are derived from the: Which of the following is not one of the factors that need to be considered to improve qua..
|
What are potential benefits of recognizing
: What are potential benefits of recognizing and eliminating non-value added activities for businesses?
|
Describes the real value in his performances
: Robert Rauschenberg’s performance art can be said to be disjunctive and almost random. Which of the following statements best describes the real value in his performances?
|