The average time for the 20 missile guidance controls

Assignment Help Operation Management
Reference no: EM13321260

United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 4,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,200 hours and cost $21,000 in materials and equipment usage. Labor cost is charged at $18 per hour.

The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls.

a. What will the last unit cost to build?

b. What will be the average time for the 20 missile guidance controls?

c. What will the average cost be for guidance control for the 20 in the contract?

Reference no: EM13321260

Questions Cloud

Suppose you hold a corporate bond that is convertible into : Suppose you hold a corporate bond that is convertible into the firm"s stock. Stock prices are falling and interest rates are also falling. Would it be a good idea to exercise your conversion option under these conditions? Why?
Evaluate the pressure of oxygen for a system in equilibrium : Calculate the pressure of oxygen for a system in equilibrium in which [NH4+] = [NO3-] at pH 7.00
Find his expected yield assuming the bond is sold in 2 year : David Hoffman purchases a $1,000 20-year bond with an 8 percent coupon rate (annual payments). Yields on comparable bonds are 10 percent. David expects that
Derive equation for the torque in terms including resistance : A movable cone fits inside a stationary conical depression. If a torque is applied to the cone, the cone will rotate at a certain speed depending on the angles θ and β, the radius r o, and the viscosity μ of the liquid.
The average time for the 20 missile guidance controls : What will be the average time for the 20 missile guidance controls
Explain the two types of interest rate risk : Define interest rate risk. Explain the two types of interest rate risk. How can an investor with a given holding period use duration to reduce interest rate risk?
Explain when mg is added directly to the beaker of hcl : What quantity of useful work can be obtained when Mg is added directly to the beaker of HCl. How can you harness this reaction to do useful work
How different is your answer from the actual price change : Calculate the duration for a $1,000, 4-year bond with a 4.5 percent annual coupon, currently selling at par. Use the bond"s duration to estimate the percentage change in the bond"s price for a decrease
Discuss how the nec3 form of contract provides stimulus : Discuss how the NEC3 form of contract provides stimulus to good management and compare and contrast this where possible with other forms of contract.

Reviews

Write a Review

Operation Management Questions & Answers

  A company manufactures a product using two machine cells

A company manufactures a product using two machine cells. Each cell has a design capacity of 250 units per day and an effective capacity of 230 units per day.

  Illustrate what should johnson estimate time

Johnson was asked to bid on a follow-on contract for another dozen receiver/transmitter units. Ignoring any forgetting factor effects, illustrate what should Johnson estimate time also parts costs to be for the dozen units.

  Determine the capabilities of information systems

Determine the capabilities of information systems and explain how they can be used to improve an organization's ability to fulfill its mission and compete in its industry.

  After searching the supplier directory

After searching the supplier directory, use specific criteria to compare the profiles of companies supplying both red and white. Decide which supplier is best for your company. Be sure to justify your conclusion.

  What are the positive and negative impact of tariffs

What are the positive and negative impact of tariffs. Give a specific example of each.

  What feedback did you receive

In 100 words or less, please describe a team situation, which has included the type of people you find it difficult to work with. What impact did this have on team performance? How successful were you? What feedback did you receive?

  What strategies does a company need to develop

What strategies does a company need to develop to become a broad differentiator? In what ways does this provide the company with a competitive advantage over cost leaders? Over differentiators?

  Compute percentage of the pieces to meet length specs

Specifications for a piece of material used in the manufacture of a bed mattress require that the piece be between 59.28 and 60.72 inches. The process that produces the piece yields a mean of 60 and a standard deviation of 0.6 inches.

  What is the error on each day

Prepare a three-peroid moving average forcast for the data. What is the error on each day?

  Differentiate between hedgers and speculators

When calculating a local basis, the trader must take into consideration a number of variables. Briefly describe each of the variables that can influence the basis.

  Which of the following generally applies the same criteria

Which of the following generally applies the same criteria to acceleration as to initial unit determination?

  How many units are needed to break even if each complete

How many units are needed to break even if each completed unit has a value of $100?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd