TELOXY ENGINEERING (A)

Teloxy Engineering has received a one-time contract to design and build 10,000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. One of the ingredients necessary to build the product was a small component that could be purchased for $60 in the marketplace, including quantity discounts. Accordingly, management budgeted $650,000 for the purchasing and handling of 10,000 components plus scrap.

During the design stage, your engineering team informs you that the final design will require a somewhat higher-grade component that sells for $72 with quantity discounts. The new price is substantially higher than you had budgeted for. This will create a cost overrun.

You meet with your manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. Your manufacturing team informs you that they can produce a maximum of 10,000 units, just enough to fulfill your contract. The setup cost will be $100,000 and the raw material cost is $40 per component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects:

Percent defective- 0 10 20 30 40

Probability of occurrence- 10 20 30 25 15

All defective parts must be removed and repaired at a cost of $120 per part.

1. Using expected value, is it economically better to make or buy the component?

2. Strategically thinking, why might management opt for other than the most economical choice?

Reference no: EM132603732

Questions Cloud

Business organizational strategy and projects : Define organizational strategy. Explain the relationship between a business's organizational strategy and its projects.
Venture capital as startup funding for business : Discuss the advantages and disadvantages of using venture capital as startup funding for a business.
Consistent and improve the brands : As a company's marketing manager, I would first understand the brands, be consistent and improve the brands that already exists
Evaluate the current forces driving change in your field : Evaluate the current forces driving change in your field or industry. Propose the steps needed for your organization or department to respond to driving force.
Teloxy engineering-strategically thinking : Teloxy Engineering has received a one-time contract to design and build 10,000 units of a new product. Strategically thinking
Bookkeeping and data entry : Do you need someone to organize your schedule, book travel, and arrange meetings, or are you looking for someone to help with bookkeeping and data entry?
Demonstrating knowledge of statutory interpretation : Accurate answers to the questions demonstrating knowledge of statutory interpretation, legislative and regulatory provisions and applying problem solving skills
Developing great literature review : Although you won't solidify your research design until you've completed the work involved in developing a great Literature Review,
Raw material to achieve the stated goal : For all products, you can assume that you have purchased the API; you do not need to synthesize the API and raw material to achieve the stated goal

Reviews

Write a Review

Operation Management Questions & Answers

  Key questions would you ask the previous project manager

You have been assigned as the new Project Manager to a $20M, 3 year project that is 6 months behind schedule and $1M over budget after one year. What three key questions would you ask the previous project manager? (b) What would you tell the customer..

  Estimate the average number of customers at facility

Consider a production line with two facilities in series. (A facility is the same as a station.) Every customer or job requires service first at facility 1 and then at facility 2. The mean and std. deviation of the effective service time at facility ..

  Keeping-charting as they relate to advancement in technology

Provide an analysis of the current trends in health care record keeping and charting as they relate to advancements in technology.

  Methods to rate contract performance and compliance

Despite the benefits of diversity, some say it is a “double-edged sword.” Explain why. Describe the tools and methods to rate contract performance and compliance. Briefly discuss which you think has the most impact on a person's lived experience- rac..

  Dubrin and goleman addressed the issue of intelligence

Discuss the major differences between Goleman’s emotional intelligence and DuBrin’s discussions of cognitive intelligence?

  About critical design flaw with artificial hip

About a critical design flaw with an artificial hip but decided to conceal this information from physicians and patients.

  Discuss the company social value in general

Discuss the Company Social Value in general, and apply it to your chosen company in particular.

  Firm builds small facility and demand turns out

A firm must decide whether to construct a small, medium, or large stamping plant. A consultant’s report indicates a .20 probability that demand will be low and an .80 probability that demand will be high. If the firm builds a small facility and deman..

  Binding constraints intersect to form the

Geometrically, binding constraints intersect to form the

  Article on the topic of human resources management

Conduct a search within the CSU-Global Library or on the internet and locate at least one article on the topic of human resources management. The article is to be published in an HR-related journal or industry-related periodical. Highlight any new in..

  Illustrate the organizations product portfolio

Discuss the ethical implications of the organization's policies and strategies with respect to market expansion, human capital management, and the environment.

  Project time schedule for project management plan

What elements should be included in a Project Time Schedule for a Project Management Plan? Please be very specific.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd