Given the information in the table below:
Task Predecessor Duration
A 5 days
B 7
C 4
D A 6
E B 9
F B 6
G C 4
H D,E 6
I D,E 8
J F,G,H 9
K I 10
L J,K 9
a. Create an AON network.
b. Create a table with 10 columns: Task Name, Duration, Start, Finish, ES, EF, LS, LF, Free Slack, and Total Slack. All dates should be specific calendar dates.
c. List all the critical paths.
d. How many days is the project duration?
Assume that the project starts on 1/1/2010. Furthermore, assume a 7-day week calendar. This means that there are no holidays or weekends, and that project tasks may fall on weekends or holidays.
Specify ES, EF, LS, and LF in terms of calendar dates.
Patient care management-strategic planning
: Communication/relationship building, Patient care management, Strategic Planning, Organizational Performance
|
Any problems with the reward process
: Any problems with the reward process ? Anybody tried redeeming their points without inconvenience ? Are there any electronic vouchers here ?
|
Changes require enhancement of adult learning
: Burns in HRMonthly Magazine was quoted in saying 'conceives of learning as a relatively permanent change in behavior with behavior including both observable activity and internal processes such as thinking, attitudes and emotions.
|
Business managers lead marketing-engineering operations
: Adelphi Technologies is a software product company with about 50 employees, marketing Products A and B. Each product has a business manager reporting to the CEO. The business managers lead marketing and engineering operations.
|
Task predecessor duration-create an aon network
: Create an AON network. Create a table with 10 columns: Task Name, Duration, Start, Finish, ES, EF, LS, LF, Free Slack, and Total Slack. All dates should be specific calendar dates. List all the critical paths.
|
Business strategy-mission-vision-organizational structure
: Summarize the company’s business strategy, mission, vision, culture, and organizational structure (include size, type of employees). Discuss how you would plan and organize the five distinct phases of the System Development Life Cycle (SDLC). Discuss..
|
How does descartes respond to princess elizabeth
: In your own words, give an account of Princess Elizabeth’s criticism of Descartes. How does Descartes respond to Princess Elizabeth? Is this response adequate, in your opinion? Explain.
|
The three reasons as to why rhetoric is important
: The three reasons as to why rhetoric is important: because it is necessary to a vital democracy, it helps people seek justice, and it helps people clarify their own ideas and beliefs. Which of these three reasons do you believe is the most important ..
|
What are the seven steps to determining information
: What are the seven steps to determining information? Its in a book called the social factor. Its an IT class I am taking.
|