Systems Implementation and Operation

Jim Watanabe was in his new car, driving down I-5, on his way to work. He dreaded the phone call he knew he was going to have to make.

The original go-live date for a pilot implementation of Petrie’s Electronics’ new customer relationship management (CRM) system was July 31. That was only six weeks away, and Jim knew there was no way they were going to be ready. The XRA CRM they were licensing turned out to be a lot more complex than they had thought. They were behind schedule in implementing it. Sanjay Agarwal, who was a member of Jim’s team and who was in charge of systems integration for Petrie’s, wanted Jim to hire some consultants with XRA experience to help with implementation. So far, Jim had been able to stay under budget, but missing his deadlines and hiring some consultants would push him over his budget limit.

It didn’t help that John Smith, the head of marketing, kept submitting requests for changes to the original specifications for the customer loyalty program. As specified in the project charter, the new system was supposed to track customer purchases, assign points for cumulative purchases, and allow points to be redeemed for “rewards” at local stores. The team had determined that those rewards would take the form of dollars-off coupons. Customers who enrolled in the program would be given accounts that they could access from Petrie’s Web site. When they signed on, they could check their account activity to see how many points they had accumulated. If they had earned enough points, they were rewarded with a coupon. If they wanted to use the coupon, they would have to print it out on their home printers and bring it in to a store to use on a purchase. The team had decided long ago that keeping everything electronic saved Petrie’s the considerable costs of printing and mailing coupons to customers.

But now marketing had put in a change request that would give customers a choice of having coupons mailed to them automatically or printing them from the Web site at home. This option, while nice for customers, added complexity to the XRA system implementation, and it added to the costs of operation. Jim had also learned yesterday from the marketing representative on his team, Sally Fukuyama, that now Smith wanted another change. Now he wanted customers to be able to use the coupons for online purchases from Petrie’s Web site. This change added a whole new layer of complexity, affecting Petrie’s existing systems for ordering online, in addition to altering yet again the implementation of the XRA CRM.

As if that wasn’t enough, Carmen Sanchez was now telling Jim that she would not be ready to let the team pilot the system in her Irvine store. Carmen was saying her store would not be ready by the end of July. Maybe that wouldn’t matter, since they were going to miss the go-live date for the pilot. But Carmen was hinting she would not be ready for months after that. It seemed as if she didn’t want her store to be used for the pilot at all. Jim didn’t understand it. But maybe he should try to find another store to use as the pilot site.

Jim was almost at his exit. Soon he would be at the office, and he would have to call Ella Whinston and tell her the status of the project. He would have to tell her that they would miss the go-live date, but in a way it didn’t matter since he didn’t have a pilot location to go live at. In addition to going over schedule, he was going to have to go over budget, too. He didn’t see any way they would be ready for the pilot anytime close to when they had scheduled, unless he hired the consultants Sanjay wanted. And he would have to stop the latest change request filed by marketing. Even more important, he would have to keep the rumored change request, about using coupons for online purchases, from being submitted in the first place.

Maybe, just maybe, if he could hire the consultants, fight off the change requests, and get Carmen to cooperate, they might be ready to go live with a pilot in Irvine on October 15. That gave him four months to complete the project. He and the team were going to have to work hard to make that happen.

Jim realized he had missed his exit. Great, he thought, I hope it gets better from here.

Petrie Electronics implemented its Customer Relationship Management (CRM) system, No Customer Escapes last week. But like any system, the Change Management team receives a request for a change to the system. The Project Manager reviews the change request, and realizes an alternative development method is needed to analyze and design the changes to the system. An object oriented method must be selected, but it seems Use Cases were not created when the system was first developed. The Project Manager knows the benefits of Use Cases and assigns our team to create one using Unified Modeling Language (UML) notation.

1. In Week 7, we learn some alternative system development life cycle (SDLC) methods, object-oriented analysis and design, and agile methods.

In order to implement our CRM system, we will need to create a Use-Case Diagram illustrating the four processes the CRM system identified in our book

Reference no: EM13901559

Questions Cloud

How many total subjects should be studied : How many total subjects should be studied to have 80% power for detecting a reduction of 10 mmHg in SBP due to exercise, assuming a 0.01 type I error and 2-sided alternative hypothesis? Briefly describe the approach you used
Discuss the merit and shortcoming of the managerial practice : Firms often provide supplemental disclosures that report and discuss income figures that do not necessarily equal bottom-line net income from the income statement. Discuss the merits and shortcomings of this managerial practice.
Accounting-human resource-supply chain and marketing team : For many months, your prospective ERP customer has been analyzing the hundreds of assumptions built into the $900,000 ERP software you are selling. So far, you have knocked yourself out to try to make the sale. At the very least, the customizing will..
What are possible shortcomings of using common-size analysis : Common-size analysis is a simple way to make financial statements of different firms comparable. What are possible shortcomings of comparing two different firms using common-size analysis?
Systems implementation and operation : The original go-live date for a pilot implementation of Petrie’s Electronics’ new customer relationship management (CRM) system was July 31. That was only six weeks away, and Jim knew there was no way they were going to be ready. In Week 7, we learn ..
Question regarding the solid waste engineering : If the waste in a landfill has an un-compacted bulk density of 8.3 lb/ft3 and the landfill compaction is 1400 lb/yd3, how much volume reduction is achieved by compaction?
What are the competitive priorities for custom molds : What are the competitive priorities for Custom Molds' processes and the changing nature of the industry? What alternatives might the Millers pursue? What key factors should they consider as they evaluate these alternatives? Do you think that their so..
Weaknesses should be determined relative to competitors : Strengths and weaknesses should be determined relative to competitors, or by elements of being, or relative to a firm's own objectives. Explain.
Comparing and contrasting worst vs. best communicators : Craft a 600-800 word paper comparing and contrasting “worst” vs. “best” communicators, deciding on key points, then using the all sources provided and tying to course concepts from the text. What do you admire most about effective communicators? What..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd