System design checkpoint review

Assignment Help Business Management
Reference no: EM132075596

Software Development Specialists (SDS) is involved with developing software for customers in the banking industry. SDS breaks a large programming project into teams that perform the necessary steps. Team A is responsible for going from general systems design all the way through to actual systems testing. This involves 18 separate activities. Team B is then responsible for the final installation. To determine cost and time factors, optimistic, most likely, and pessimistic time estimates have been made for all of the 18 activities involved for team A. The first step that this team performs is general systems design. The optimistic, most likely, and pessimistic times are 3, 4, and 5 weeks. Following this, a number of activities can begin. Activity 2 is involved with procedures design. Optimistic, most likely, and pessimistic times for completing this activity are 4, 5, and 12 weeks. Activity 3 is developing detailed report designs. Optimistic, most likely, and pessimistic time estimates are 6, 8, and 10 weeks. Activity 4, detailed forms design, has optimistic, most likely, and pessimistic time estimates of 2, 5, and 5 weeks.

Activities 5 and 6 involve writing detailed program specifications and developing file specifications. The three time estimates for activity 5 are 6, 7, and 8 weeks, and the three time estimates for activity 6 are 3, 4, and 5 weeks. Activity 7 involves specifying system test data. Before this is done, activity 6, involving file specifications, must be completed. The time estimates for activity 7 are 2, 3, and 7 weeks. Activity 8 involves reviewing forms. Before activity 8 can be conducted, detailed forms design must be completed. The time estimates for activity 8 are 3, 3, and 9 weeks. The next activity, activity 9, is reviewing the detailed report design. This requires that the detailed report design, activity 3, be completed first. The time estimates for activity 9 are 1, 3, and 5 weeks, respectively. Activity 10 involves reviewing procedures design. Time estimates are 1, 2, and 9 weeks. Of course, procedures design must be done before activity 10 can be started. Activity 11 involves the system design checkpoint review. A number of activities must be completed before this is done. These activities include reviewing the forms, reviewing the detailed report design, reviewing the procedures design, writing detailed program specs, and specifying system test data. The optimistic, most likely, and pessimistic time estimates for activity 11 are 3, 4, and 5 weeks. Performing program logic design is activity 12. This can be started only after the system design checkpoint review is completed. The time estimates for activity 12 are 4, 5, and 6 weeks.

Activity 13, coding the programs, is done only after the program logic design is completed. The time estimates for this activity are 6, 10, and 14 weeks. Activity 14 is involved in developing test programs. Activity 13 is the immediate predecessor. Time estimates for activity 14 are 3, 4, and 11 weeks. Developing a system test plan is activity 15. A number of activities must be completed before activity 15 can be started. These activities include specifying system test data, writing detailed program specifications, and reviewing procedure designs, the detailed report design, and forms. The time estimates for activity 15 are 3, 4, and 5 weeks. Activity 16, creating system test data, has time estimates of 2, 4, and 6 weeks. Activity 15 must be done before activity 16 can be started. Activity 17 is reviewing program test results. The immediate predecessor to activity 17 is to test the programs (activity 14). The three time estimates for activity 17 are 2, 3, and 4 weeks. The final activity is conducting system tests. This is activity 18. Before activity 18 can be started, activities 16 and 17 must be complete. The three time estimates for conducting these system tests are 2, 6, and 7 weeks. How long will it take for team A to complete its programming assignment?

Reference no: EM132075596

Questions Cloud

What are the major differences between pert and cpm : 1. What are some of the questions that can be answered with project management?
What are the est and lst : 1. What are the EST and LST? How are they computed? 2. Describe the meaning of slack and discuss how it can be determined.
Develop a detailed implementation plan : In this final week, you have one more major task. Develop a detailed project plan for all of the final implementation, acceptance confirmation.
What is the probability that the project will : The expected project completion time for the construction of a pleasure yacht is 21 months, and the project variance is 6.
System design checkpoint review : This can be started only after the system design checkpoint review is completed. The time estimates for activity 12 are 4, 5, and 6 weeks.
Semesters or quarters for particular school : How long do you think it will take you to graduate? Which courses, if not taken in the proper sequence, could delay your graduation?
Expected completion time for the entire process : Given this information, determine the expected completion time for the entire process. Also determine which activities are along the critical path.
Explain the key aspects of supply-chain management : 1. Explain the key aspects of supply-chain management. 2. Contrast the use of ocean shipping and airfreight.
Write your response on a new wireless network : Suppose your neighbor upgraded to a new wireless network and did not make it secure. Is it ethical for you to tap into his/her network.

Reviews

Write a Review

Business Management Questions & Answers

  Noteworthy lessening in the quantity of base

An assessor assessing arbitrarily chose research center reports for as far back as year saw a noteworthy lessening in the quantity of base/nonpartisan and corrosive extractable examples requiring re-extraction on account of low surrogate recuperat..

  Explain linear and non linear trend patternscan you explain

explain linear and non linear trend patterns.can you explain linear and non linear trends patterns and give an example

  Review the company scenario at the beginning of the course

Review the company scenario at the beginning of the course for additional information regarding growth goals.

  Evolution of international agreements

Explain what is meant by "Open Skies" and discuss the evolution of these international agreements affecting access to world aviation markets. Compare "Open Skies" arrangements with bilateral agreements.

  Business case report - writing the business case

your group is required to identify a business and the business stakeholder you will be writing the business case for

  Explain and prepare a memo to the ceo explaining

Explain and Prepare a memo to the CEO explaining the three options the company can choose from and what your recommendation is

  Bob drags the exercise bike over to the television

Bob drags the exercise bike over to the television. He stands on the seat of the exercise bike in order to reach the television, but the seat post breaks and Bob falls to the floor.

  Addressing organizational change with lewins change

addressing organizational change with lewins change modelusing an example of how the lewins change model is applied

  Explanation of introduction including company description

Topic is Dell project. Need only the explanation of introduction including Company's description and problem statement

  Show bureaucracy in healthcare

Bureaucracy in Healthcare - Classical bureaucracy has been the defining hall-mark of health services organization.

  Explain how a project risk management approach

Explain how a project risk management approach provides an early warning signal for impending problems or issues

  Members informed regarding continuous improvement efforts

List three methods your group has used to keep your project group members informed regarding continuous improvement efforts. Explain why these methods were used and whether they were effective.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd