Utilizing the Step-by-Step MRP Calculation Process, students will solve the following MRP problem given: Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. Product C is made of two units of F and two of E. Product A has a lead-time of one week. Products B, C and E have lead-times of two weeks. Products D and F have a lead-time of three weeks.
a. Show the bill of material (product structure tree). b. If 100 units of A are required in week 10, develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.
Verified Expert
The report is a sample work to find the BOM as well as MRP of a given product. MRP is estimated from the data given for the manufacturing of a product and MRP is also estimated from the lead times given in the data. The findings are tabulated in the report. References provided as appropriate.
Indifference point in make/buy decisions is determined by what condition: Dell computer corporation operations demonstrates that supply chain can
Job E has a processing time of 5 days and is due in 12 days. Using the shortest processing (operating) time priority rule, what will be the average number of jobs in the system?
Illustrate what is the process cycle time. If the firm operates 10 hours per day, 5 days per week, illustrate what is the weekly capacity of this work cell.
research the process of producing an expensive product assume that it is something that must cost at least 1000. after
Some have argued the Six Sigma programs are merely repackaged versions of older quality improvement programs that originally accompanied TQM initiatives in the 1980s. Present arguments that both support and refute this view.
Evaluate sales necessary to equal dollar of savings on purchases for a company which has a net profit of 4% also spends 40% of its revenue on purchases.
A part used to repair machines has a normally distributed monthly demand with a mean of 65.0 and a standard deviation of 5.2. If lead-time is so predictable that it can be considered a constant 0.25 month and service level is 90 per cent: Illustra..
If it is working today, what is the probability that it will be working two days from now
Formulate the linear programming problem to maximize the profit during the coming month. Write all of the constraints that are indicated by the above description of the problem.
What elements discussed in the case study are important for someone who works in the field of human resources? How do the results of the quiz compare to what the case study states is ideal?
Up to three standard deviations above or below the centerline is the amount of variation that statistical process control allows for
synthesis of the information evaluating the ability of the organization to implement the strategy using Kouzes and Posner's Five Practices
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd