State the name and length of the critical path

Assignment Help Operation Management
Reference no: EM133244208

Your project sponsor has been so impressed with your project management work that you have been tasked to assist Project Ecommerce. The project manager for Project Ecommerce does not know how to create a Project Schedule Network Diagram. To assist the other project, use the information in the table below to answer the questions that follow.

Activity Duration (in weeks) Predecessor
A 2 -
B 3 A
C 6 A
D 8 C
E 3 B
F 4 C, E
G 2 F
H 4 E, G
I 4 G
J 2 D, I

To assist the other project, answer these questions:

Prepare a (simple) Activity on Node diagram as demonstrated in the chapter video.
Name, state the length and slack for each path in the diagram.
Explain the term Critical Path.
State the name and length of the Critical Path.

Reference no: EM133244208

Questions Cloud

When you look back on your learning experiences in past jobs : When you look back on your learning experiences in past jobs, how have the theories that were popular at the time affected how decisions and choices were made b
Understand the different purposes a firm : Why is it vital that the consultant understand the different purposes a firm can serve in emerging (and frontier) markets?
Identify all of stakeholders associated with that project : Briefly explain a project (or group activity) where you have been a stakeholder. Identify all of the stakeholders associated with that project based on the defi
Constraints to the logistics service of medical record : Applying the Theory of Constraints to the Logistics Service of Medical Record ... (Canvas/Module 0/ Course Resource (1))
State the name and length of the critical path : Your project sponsor has been so impressed with your project management work that you have been tasked to assist Project Ecommerce. The project manager for Proj
Find additional descriptions and ratings : A variety of modern tools for big data analytics exist in the market today. The following are well-known analytics tools, and you will find additional descripti
What is the method the author is using : In the article, "the rise and fall of the great powers in the twenty first century" what is the main argument that the author is making
Discuss the practical nature of common legal issues : Discuss the practical nature of common legal issues and challenges in PNG relating to trust properties and finances.
Evaluate the main arguements surrounding : Evaluate the main arguements surrounding ONE first amendment debate. Use case examples and evaluate the strengths and weaknesses on both sides.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd