Reference no: EM13790615
A Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 1,900 units of Product B was received. The standard cost of one unit of Product B is as follows.
Direct Materials 3 pounds at $1.00 per pound $3.00
Direct Labour 1 hour at $8.00 per hour 8.00
Overhead 2 hours (variable $4.00 per machine hour; 12.50 fixed $2.25 per machine hour)
Standard cost per unit $23.50
Normal capacity for the month was 4,200 machine hours. During January, the following transactions applicable to Job No. 12 occurred.
1. Purchased 6,200 pounds of raw materials on account at $1.05 per pound.
2. Requisitioned 6,200 pounds of raw materials for Job No. 12.
3. Incurred 2,000 hours of direct labor at a rate of $7.80 per hour.
4. Worked 2,000 hours of direct labor on Job No. 12.
5. Incurred manufacturing overhead on account $25,000.
6. Applied overhead to Job No. 12 on basis of standard machine hours allowed. 7. Completed Job No. 12.
8. Billed customer for Job No. 12 at a selling price of $65,000.
Instructions
(a) Journalize the transactions.
(b) Post to the job order cost accounts.
(c) Prepare the entry to recognize the total overhead variance.
(d) Prepare the January 2014 income statement for management. Assume selling and administrative expenses were $2,000.
Retirement fund by depositing
: Sara decides to set up a retirement fund by depositing $21 at the end of each day for 17 years. How much will she have then, if the interest rate is 6.25% compounded weekly and her account starts with $14,500 already deposited?
|
Used to offset passive activity income
: Passive activity losses generally can only be used to offset passive activity income. However in certain circumstances activities that would generally be considered a passive activity may not be subject to the passive activity loss rules. What will t..
|
The current contract amount for the project
: The current contract amount for the project is $150,000. The estimated cost at completion is $130,000. The actual costs to date are $47,000 and the total billed to the owner is $55,000. Is the project over or under billed? By how much?
|
Construction accounting and financial management
: Determine the marginal tax rate for a corporation whose federal tax rate is 34% and whose state tax rate is 11%. Explain the rationale for having a separate cost code for site concrete-labor and site concrete-concrete as is the case in Figure 2-6 fro..
|
Standard costs with its job order cost accounting system
: A Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 1,900 units of Product B was received. Prepare the January 2014 income statement for management. Assume selling and administr..
|
Difference in cash flow and deductibility for tax purposes
: Calculate the annual difference between the cash flow and the deductibility for tax purposes for the purchase of a $60,000 dump truck. The truck is depreciated using the half-year convention and 200% declining-balance. The truck is purchased outright..
|
Calculate the net present value for the dump truck
: Your company is looking at purchasing a new dump truck for $70,000. The dump truck has an hourly operation cost (including operator) of $45.00 per hour and a useful life of five years. At the end of five years the truck has a salvage value of $10,000..
|
Regarding the budgeted cost for direct materials
: Which of the following statements is true regarding the budgeted cost for direct materials?
|
Disadvantage of decentralization
: Which of the following is a disadvantage of decentralization?
|