Standard costs for direct materials for january production

Assignment Help Managerial Accounting
Reference no: EM13939232

The following company information is available for January:

Direct materials used..................$2,300 feet @$50 per foot
Standard costs for direct materials for January production ...$2,400 feet @ $48 per foot

The direct material price variance is: 

a. $7,600 unfavorable. 
b. $6,350 favorable. 
c. $4,600 unfavorable. 
d. $4,700 favorable. 
e. $4,350 favorable.  

Reference no: EM13939232

Questions Cloud

Pspecs for elementary processes : Borrow a document, Return a document, Reserve a document , De-register a reader, and (if there are five members) ; Archive a document. Having selected one of the above functions, you are asked to prod..
Find the pressure at each end : A swimming pool has depths of 4.0 feet and 12.0 feet at the shallow and deep ends, respectively. Find the pressure in lb/ft2 at each end.
What differences between diastolic and systolic pressure : What are some differences between diastolic and systolic pressure? Trace the flow of blood from the superior and interior vena cava to the lungs and back to the aortic arch.
Market plan, and define the target gorup : This most not include front page and table of content please. what you have to do for me in this case is 1.Global Economy of Mexico in-dept pestel insignt market line explain why is an important factor.
Standard costs for direct materials for january production : Standard costs for direct materials for January production.
Increasing sophistication and complexity of businesses : You are required to consider the challenges facing contemporary auditors under the following headings: The increasing sophistication and complexity of businesses.
Prepare a press release announcing the product : Prepare a press release (max 1 Page) announcing this product and identify at least 5 publications and contacts at those publications (max 1 page) for this release.
Evaluate the headwater depth : The culvert has a length of 105 feet, slope of 0.75 percent, and 45 degree wingwalls with square edge. Tailwater depth is 4.1 feet. Find the headwater depth.
Structure of a network to support the various operations : You need to set up the structure of a network to support the various operations and in particular video conferencing using the multicast backbone. Part of the work also includes answering some technical questions.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd