The Space Age Furniture Company manufactures tables and cabinets to hold microwave ovens and portable televisions. These products are made in various sizes and with various features, but all follow basically the same production and assembly operations. However, two of these products-the Saturn microwave stand and the Gemini TV stand-have a part (no. 3079) that requires machining on a special lathe used only for making that part. At present the machine is run by Ed Szewczak, a machinist who also operates other machines in Space Age's shop. Once set up and started, the lathe can run nearly unattended. However, the machinist must be present (even if not actually attending the machine) any time one of the machines, including the lathe, is in operation. At present, Ed works a regular 40-hour week. However, due to the workload for producing part 3079, it has been necessary to schedule frequent overtime for him in order to finish the necessary parts on time. Coral Snodgrass, operations manager for Space Age, has just heard from Ed's foremen that Ed is becoming unhappy about so much overtime. As Coral knows, Ed has been with the company a long time and is an excellent, reliable employee. Skilled machinists with Ed's experience and employment record are extremely difficult to find. Coral wonders what can be done to alleviate this problem. Recently, Space Age began using an MRP system that has helped reduce inventories greatly and improve on-time deliveries. In fact, Space Age carries no finished-goods inventory. Instead, everything in the master schedule is being produced for customer orders, so all products are shipped almost immediately. Previously Space Age had estimated that it cost $1.25 per week to store each Gemini and $1.50 per week to store each Saturn that wasn't shipped immediately. The master schedule for producing these two items for the next six weeks is shown below.
Master Schedule
Week
1 2 3 4 5 6
Gemini 600 400 700 500 400 600
Saturn 300 400 400 600 300 300
The part in question, 3079, is used in two different subassemblies: no. 435, which is used in the Gemini TV stand, and no. 257, which is used in the Saturn microwave stand. One of part 3079 is used in each subassembly, and one of each subassembly is used in each of the final products.Part 3079 may be produced in any quantity since the lathe that makes it is not used for anything else. However, both of the subassemblies are produced using the same equipment. To minimize change over time, Space Age has decided that these subassemblies should be made in minimum quantities of 1,000 at a time, although there is no problem with capacity on the equipment that makes them. In fact, an order for 1,000 of subassembly 435 is due to be received in week 1, as is an order for 1,000 of subassembly 257. Lead time for both these subassemblies is one week, and no inventory is expected to be on hand for either part at the beginning of week 1. There is not any on-hand inventory of part 3079, and there are no orders in process.Ed Szewczak earns $22 per hour and gets a 50% premium for any overtime work. Whenever part 3079 is made, there is no set-up time, but processing takes 0.03 hour per unit. It costs $0.25 per week to hold any of these parts over from one week to the next. The cost of holding each subassembly in inventory is $0.75 per unit per week.
Instructions:
Read and answer the 4 questions in double space with calculations included in APA format with references if used. Times Roman 12 point 5 pages.
1. Develop an MRP for Space Age Furniture Company using the information in the case including the production of sub-assemblies in lot sizes of 1,000.
2. The lot size of 1,000 for sub-assemblies has produced a lumpy demand for part 3079. Suggest ways for improvements over sub-assemblies in lot sizes of 1,000.
3. Analyze the trade-off between overtime costs and inventory costs.
4. Calculate a new MRP that improves the base MRP.

Reference no: EM13340910

Questions Cloud

What is coefficient of friction between rock and icy ground : A 70-kg climber is hanging by a rope off the edge of a cliff, with the top end of the rope tied to a 200-kg rock. However, the rock is sitting on an icy horizontal surface,
Advantages and disadvantages of a standard costing system : Construct an Excel or other spreadsheet to demonstrate how the solution to part 1 would change if the following information changes:the actual labour rates were $27.00, $22.90 and $17.00 for labour classes 3,2 and 1 respectively.
Is it ethical for gina to revise the costs : Who are the stakeholders in this decision and is it ethical for Gina to revise the costs as indicated - Prepare an analysis showing whether the old machine should be retained or replaced.
Explain the naoh solution what is the molarity : A solution is prepared by dissolving 21.9 NaOH in 116.0 water. The NaOH solution has a density of 1.15g/mL. What is the % mm concentration of the NaOh solution What is the molarity (M) of the solution. What is the total volume (mL) of the solution
Space age furniture company : Space Age Furniture Company
What is the total work done by the compressor motor : In the meantime, this means the refrigerator produces 1.2177E+4 J of thermal energy that it expels into the kitchen as a result. What is the total work done by the compressor motor in the refrigerator
Determine the average electric field strength : A laser emits 7.50 × 1017 photons per second in a beam of light that has a diameter of 1.89 mm and a wavelength of 514.5 nm. determine the average electric field strength
Calculate the mass of satellites planet from the information : A certain satellite travels in an approximately circular orbit of radius 9.1 × 106 m with a period of 8 h 39 min. Calculate the mass of its planet from this information.
Explain the reactions is a combination reaction : Which one of the following reactions is a combination reaction. a. A + B -› AB b. AB + CD -› AD + CB c. HX + BOH -› BX + H2O d. A + BC -› B + AC e. AB -› A + B

Reviews

Write a Review

Management Theories Questions & Answers

  Roger works for a business software firm

Roger works for a business software firm and is passionate about his work. He is committed to delivering high-quality software solutions on schedule. He maintains a precise and accurate project schedule with meticulously detailed documentation of pro..

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  .compare the three major models of staffing found in reading

This Discussion concentrates on best practices from a series of questions from the readings. These readings seem well supported with research and have widespread application, hence the emphasis in this assignment on these practices.

  The merchant needs the database

You have been asked to explore three database alternatives for a merchant who provides shoes to retail stores. The merchant needs the database to keep the financial records, employee records, inventory records and general use records for the business

  Explain strategic asset management

What do you mean by the term strategic asset management(SAM)? Is SAM in private sector vary from that of the of the Private sector and why?

  Leadership and transformation

Explain yourself before your transformation experience. Explain your transformational experience (make sure this is an experience you are comfortable sharing).

  Top management for approval

You've completed your IMC plan, and now you have to present it to top management for approval. Create a presentation that covers the key points of your plan.

  Standards of pollution control

Suggest reasons a business may conduct operations in a third world country and disregard any standards of pollution control

  Federal healthcare organizations

Federal Healthcare Organizations

  Theories is least relevant to merit pay

Which of the following theories is least relevant to merit pay?

  Diversity in the workplace

Diversity in the Workplace

  Quality management and continuous improvement

Quality management and continuous improvement

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd