Critical Path and PERT
1) A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. The probability that the project can be completed between days 108 and 120 is
a) 0 -2.00b) 0.0227c) 0.1058d) 0.4773e) 0.9773
2) A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is
a) 0.0228b) 0.3446c) 0.6554d) 0.9772e) 18
3) Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day ________.
a) 98b) 108c) 109d) 115e) 118
find the probability that his or her birthday is not in May. If a person is randomly selected, find the probability that his or her birthday is not in May.
Statistics: Populations, Samples, Parameters and Assessing the Mean. The average time before hittin a jackpot at the local casino was estimated by using the average time that it took the first 100 players. Based on this information identify.
Provide Description of Card Probability. What is the probability that exactly one suit is represented among these 8 cards? Exactly 2 suits?
Conversion of angle measures from degrees to radians - Fill in the missing blanks by using the conversions between radians and degrees to find your solutions
A cyclic group is a special kind of group that has many similarities with modular arithmetic.
Determine the equation for 9(t) thus obtaining differential equations for the functions x(t) and y(t). What initial conditions do these functions satisfy at t = 0?
Make a new variable called BMIDIFF by computing the BMI difference for each twin pair.
Calculate the mean of this sampling distribution
Find the test statistics
A random sample of 48 days taken at a large hospital shows that averages of 38 patients were treated in the emergency room per day. The standard deviation for the population is four. Determine the 99% confidence interval of the mean number of patient..
Calculate the exact values.
Suppose that you select 3 cards without replacement from an ordinary deck of playing cards. If the first card that you select is a spade and the second is a heart, what is the probability that the third card that you select is a spade?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd