Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below.

Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessor
A 4 3 2,000 2,600 -
B 5 3 2,200 2,800 -
C 3 3 500 500 -
D 8 4 2,400 2,600 A
E 6 3 900 1,200 B
F 3 2 3,000 4,200 C
G 4 2 1,700 2,000 D,E

(a) If you wish to reduce the time required to complete this project by two weeks, which activityies should be crashed, and how much will this increase the total cost?

(b) What would be the added cost if you wanted to complete the project in the minimum time possible?

Reference no: EM13363036

Questions Cloud

What is the variance at completion for this project1 a : what is the variance at completion for this project?1. a project had a budget of 750000 and was completed on time. the
Disaster recovery plan - project manageryou have been : disaster recovery plan - project manageryou have been appointed as a project manager in charge of security setup and
Levels of qualitycompare the effort needed for the six : levels of qualitycompare the effort needed for the six levels of quality of an automobile to a toothbrush or some other
Manufacturing quality dimensionswhich of the four : manufacturing quality dimensionswhich of the four manufacturing quality dimensions are most likely to improve revenue?
Software development project managementdevelopment of a new : software development project managementdevelopment of a new deluxe version of a particular software product is being
Four factors for productionimportance to economyexplain the : four factors for productionimportance to economyexplain the four factors for production that influence a countrys
Business administrationcreate a table summarizing and : business administrationcreate a table summarizing and criticising a few programs of your choice that might help with
The time to complete a project may be shown in a chart thus : the time to complete a project may be shown in a chart thus the sequence of activities for completing the project may
Web infrastructure improvement projectthe firm will focus : web infrastructure improvement projectthe firm will focus on gathering information necessary to meet requirement of web

Reviews

Write a Review

Project Management Questions & Answers

  Project management and risk

Both internal and external factors need to be addressed as well as the probability and impact that certain risks could have on a particular project.

  Is the project worth doing

Is the project worth doing? In my job we are often reviewing whether or not we should do something and i think it's important that a project absolutely makes sense to do from either an economic or strategic standpoint.

  Computing total cost incurred

What will be the total cost incurred next year?

  What are leadership styles

The secret to being a successful manager is to use good communication skills that create a positive image. What are three leadership styles?

  Locating hub near map coordinates

Near which map coordinates should the hub be located?

  Capacity decisions affect success or failure

How might capacity decisions affect the success or failure of the restaurant?

  Write progress report about own professional accomplishments

Write a progress report about your own professional or work accomplishments. The period to be covered is last month - Assignment is to accompany Lesson 8026 Project and Progress Reports

  Techniques for risk identificationlist and describe two

techniques for risk identificationlist and describe two techniques for risk identification such as brainstorming a work

  Compute the product costs per unit

Compute the product costs per unit assuming that Tiger Furnishings uses direct labor costs and machine-hours to allocate overhead to the products. (Do not round the direct-labor cost rate in your intermediate calculations. Round your answers to..

  Earned value management to manage project costs

What is Earned Value Management (EVM)? How can EVM be used to effectively manage project costs?

  Earned value approach for variance analysis

How can the project baseline and the earned value approach for variance analysis be used to monitor and report project progress?

  Assessment into a security management program

Quality assurance is essential to any security management program and how can we incorporate quality assessment into a security management program?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd