Software development project management

Assignment Help Project Management
Reference no: EM1343073

Software Development Project Management

Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below.

Activity Normal Time Crash Time Normal Cost Crash Cost Immediate Predecessor
A 4 3 2,000 2,600 -
B 5 3 2,200 2,800 -
C 3 3 500 500 -
D 8 4 2,400 2,600 A
E 6 3 900 1,200 B
F 3 2 3,000 4,200 C
G 4 2 1,700 2,000 D,E

(a) If you wish to reduce the time required to complete this project by two weeks, which activityies should be crashed, and how much will this increase the total cost?

(b) What would be the added cost if you wanted to complete the project in the minimum time possible?

Reference no: EM1343073

Questions Cloud

What is the variance at completion for this project : What is the variance at completion for this project - Linda is a project manager for a large insurance company.
Disaster recovery plan - project manager : Plan for, and what modified internal organizational structure do you recommend to take place at the time of emergency or any disaster mishap?
Show the levels of quality : Levels of Quality - Compare the effort needed for the six levels of quality of an automobile to a toothbrush OR SOME OTHER SIMPLE ITEM.
Manufacturing quality dimensions : Manufacturing Quality Dimensions - Which of the four manufacturing quality dimensions are most likely to improve revenue?
Software development project management : If you wish to reduce the time required to complete this project by two weeks, which activityies should be crashed, and how much will this increase the total cost?
Factors for production:importance to economy : Four Factors for Production:Importance to Economy - Explain the four factors for production that influence a country's standard of living and ultimately a person's quality of life.
Show the business administration : Create a table summarizing and criticising a few programs of your choice that might help with business administration.
Sequence of activities for completing the project : The sequence of activities for completing the project may not be shown in a chart and do you agree or disagree with this statement?
Web infrastructure improvement project : Make policies and procedure to address organization web hosting needs in several locations within the organization.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd