Situation and the effect of the change request

Assignment Help Management Theories
Reference no: EM13305812

Prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following:

  • A formal change request
  • An evaluation of the impact of the change (as submitted to the Change Control Board)-time and labour only. Note: It will be necessary to create the original project schedule and budget to analyse the impact of the change request. Consider that the additional wing will be built concurrently.
  • A list of all the assumptions made
  • An analysis of risk factors due to the change request
  • A new project schedule that shows:
    • The additional time required
    • The additional labour cost
    • The new completion date
  • A statement of work for one contractor
  • A contract closure process description for one contractor
  • A project closure process description

The project details are as follows:

The Smiths decide to build a house on a piece of land that they have purchased. They have consulted with an architect and have the blueprints created. You are a general contractor and have agreed to build the house for them. The Smiths inform you that they had been considering the addition of an extra wing in the house but have now decided against it as the additional space is unnecessary. The original blueprints that the Smiths gave you did not have the additional wing.

You have projected that it will take you 12 weeks to complete the house. However, you need a buffer to accommodate the uncertain weather conditions, and you tell the Smiths that you will need 14 weeks. The Smiths are really anxious to move into their new house. Although they agree for 14 weeks, they also want to put in a penalty for late completion. You agree, provided they also put in a bonus for early completion. You reach an agreement with the Smiths, and the contract is signed. You have figured the project duration and effort as follows:

Task

Duration (days)

Effort (staff days)

Comments

Get a building permit.

5

1

 

Clear the site.

5

20

 

Dig the foundation and footings.

3

9

 

Install forms.

3

9

 

Pour concrete.

1

5

 

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

3

 

Build the floor.

1

5

 

Frame the first floor.

2

10

 

Build the second floor.

2

10

 

Frame the second floor.

3

15

 

Sheath the house.

3

12

 

Install windows and doors.

4

8

 

Install siding.

2

6

 

Put up roof framing.

2

8

Can start as soon as the second floor is framed

Shingle the roof.

1

4

 

Install plumbing.

4

8

Can start as soon as the roof is shingled

Inspect the plumbing.

1

0

 

Install wiring.

6

12

Can start as soon as the roof is shingled

Inspect the wiring.

1

0

 

Hang and finish sheetrock.

4

12

Can start only after the plumbing and electrical work are inspected

Paint the interior.

3

9

 

Lay the carpet.

2

6

 

Install the hardwood flooring.

3

6

 

Install trim.

3

6

 

Procure the certificate of occupancy.

5

0

 

Total

75

184

 

Just as your crew starts framing the second floor, the Smiths tell you that they would now like the additional wing in the house they mentioned previously. The Smiths present you with a new set of blueprints, containing the new wing and ask for a projected difference in price and time for the addition.You figure that to add the extra wing the following would be required in terms of duration and effort:

Task

Duration (days)

Effort (staff days)

Comments

Dig the foundation and footings.

2

6

 

Install forms.

2

6

 

Pour concrete.

1

3

 

Wait for the concrete to harden.

5

0

This is referred to as lag time

Remove forms.

1

2

 

Build the floor.

1

4

 

Frame the first floor.

1

4

 

Build the second floor.

1

4

 

Frame the second floor.

2

8

 

Sheath the house.

2

6

 

Install windows and doors.

2

4

 

Install siding.

1

3

 

Put up roof framing.

2

6

 

Shingle the roof.

1

3

 

Install plumbing.

2

4

 

Inspect the plumbing.

     

Install wiring.

2

4

 

Inspect the wiring.

     

Hang and finish sheetrock.

2

6

 

Paint the interior.

1

3

 

Lay the carpet.

2

4

 

Install the hardwood flooring.

     

Install trim.

1

3

 
       

Total

34

83

 

This new estimate to add the wing, assumes the sheathing will go on the base house and then work will stop until the extra wing is sheathed. You believe this will be the most economical way to add the additional wing to the property. Another option would be for the project to continue as originally planned, and then add the wing after the Smiths have moved in. After considering both options, the Smiths choose to follow your recommendation to add the new wing now so that they move in when the whole house is complete. The additional work required is as follows:

Task

Duration (days)

Effort (staff days)

Comments

Procure the building permit.

5

1

 

Dig the foundation and footings.

2

6

 

Install forms.

2

6

 

Pour concrete.

1

3

 

Wait for the concrete to harden.

5

0

 

Remove forms.

1

2

 

Build the floor.

1.5

6

 

Frame the first floor.

1.5

6

 

Build the second floor.

1.5

6

 

Frame the second floor.

2

8

 

Add the sheath.

2

6

 

Install windows and doors.

2

4

 

Install the siding.

1

3

 

Put up roof framing.

2.5

7

 

Shingle the roof.

1

3

 

Install plumbing.

2

4

 

Inspect the plumbing.

1

0

 

Install wiring.

2

4

 

Inspect the wiring.

1

0

 

Hang and finish sheetrock.

2

6

 

Paint the interior.

1

3

 

Lay the carpet.

2

4

 

Install trim.

1

3

 
       

Total

38

90

 

The rates for the various trades (in $/hour) are as follows:

Code

Description

Rate

Comments

GC

General contractor

40.00

 

HE

Heavy-equipment operator

50.00

Includes equipment

C

Concrete worker

30.00

 

F

Framer

20.00

 

F

Siding installer

20.00

 

W

Window/door installer

30.00

 

R

Roofer

20.00

 

P

Painter

20.00

 

E

Electrician

35.00

 

FL

Flooring installer

20.00

 

T

Trim carpenter

35.00

 

PL

Plumber

35.00

 

In this project, you will analyse the situation and the effect of the change request on the schedule, cost, and features. 

Reference no: EM13305812

Questions Cloud

Faith seeking understanding : Identify clearly the topic(s) you have chosen to discuss and discuss the topic in light of the teachings of the Church
How many days will the fish hatchery have to contain water : If for parathion, the activation energy is 15.4 kcal/mole and A = 8.1 x 109 at a pH = 7.8, how many days will the fish hatchery have to contain the river water if T = 15 oC (winter time)
Determine what is the required pipe size to deliver : A concrete pipeline is installed to deliver 6m^3/sec of water (10degressC) between two reservoirs 17 km apart. If the elevation difference between the two reservoirs is 12m, what is the required pipe size
Find is it virtual or real : A 2.0cm tall object is located 18.0cm in front of a converging lens with a focal length of 10.0cm. Is it virtual or real
Situation and the effect of the change request : The situation and the effect of the change request on the schedule, cost, and features.
How to calculate the forces in members ec and ef : Using method of joints, calculate the forces in members EC and EF. Note that the length of the member CD is 3.464 m, the length of member EC is 2m, and angle CDE is 30 degree ( this will cut down a bit of trigonometry effort).
What price must the division charge in order to break even : The division has fixed costs of $10,000 per month, and it expects to sell 42,000 strips per month. If the variable cost per strip is $2.00, what price must the division charge in order to break even?
What is jaster market / book ratio : It has 800 million shares of common stock outstanding,and its stock price is $32 per share. What is Jaster'smarket /book ratio?
How close will the particles get to each other : A proton is fired directly at a lithium nucleus. If the protonâ€TMs velocity is 4.0x105 m/s when it is far from the nucleus, how close will the particles get to each other

Reviews

Write a Review

Management Theories Questions & Answers

  Learning in action

Learning contract proposal that will form the basis of your learning contract report.

  Change is the only constant

"Change is the only constant " Evaluate the different types of change that have occurred in Sony.

  How do advertisers try to use group influence

How do advertisers try to use group influence?  Will you find any specific examples and explain the relevant theory of group behavior and influence?

  Case study:saving sony

You have been appointed by Sony as a consultant on change management. Advise Sony on how they could implement the change by using the various theories of change you have learnt.

  How the stock market works

The purpose of this project is to help you to gain an understanding of how the stock market works and of the relationship between theory and practice.

  Find the optimal production quantities

Find not only the optimal production quantities, but also the optimal total cost.

  Describe the management process

Describe the management process and identify the skills required to manage business organizations.

  Case study : bert''s bonsai and aquatic sport museum

Case Study : Bert's Bonsai and Aquatic Sport Museum Prepare a knowledge management system.

  Knowledge management techniques

Demonstrate understanding of the many-sided nature of knowledge management

  Theory of transtheoretical model

Demonstrate understanding of the many-sided nature of knowledge management

  Write a paper on historical trends of management

Write a paper on Historical Trends of Management.

  Theory of reasoned action

Theory of Planned Behavior and Integrated Behaviors Model

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd