Situation and the effect of the change request

Assignment Help Management Theories
Reference no: EM13305812

Prepare a project proposal on how to adjust the project schedule. The proposal should include only descriptions of the ways in which you propose to modify the project schedule. Your final project (due in Week 8) will include the following:

  • A formal change request
  • An evaluation of the impact of the change (as submitted to the Change Control Board)-time and labour only. Note: It will be necessary to create the original project schedule and budget to analyse the impact of the change request. Consider that the additional wing will be built concurrently.
  • A list of all the assumptions made
  • An analysis of risk factors due to the change request
  • A new project schedule that shows:
    • The additional time required
    • The additional labour cost
    • The new completion date
  • A statement of work for one contractor
  • A contract closure process description for one contractor
  • A project closure process description

The project details are as follows:

The Smiths decide to build a house on a piece of land that they have purchased. They have consulted with an architect and have the blueprints created. You are a general contractor and have agreed to build the house for them. The Smiths inform you that they had been considering the addition of an extra wing in the house but have now decided against it as the additional space is unnecessary. The original blueprints that the Smiths gave you did not have the additional wing.

You have projected that it will take you 12 weeks to complete the house. However, you need a buffer to accommodate the uncertain weather conditions, and you tell the Smiths that you will need 14 weeks. The Smiths are really anxious to move into their new house. Although they agree for 14 weeks, they also want to put in a penalty for late completion. You agree, provided they also put in a bonus for early completion. You reach an agreement with the Smiths, and the contract is signed. You have figured the project duration and effort as follows:

Task

Duration (days)

Effort (staff days)

Comments

Get a building permit.

5

1

 

Clear the site.

5

20

 

Dig the foundation and footings.

3

9

 

Install forms.

3

9

 

Pour concrete.

1

5

 

Wait for the concrete to harden.

5

0

This is referred to as lag time.

Remove forms.

1

3

 

Build the floor.

1

5

 

Frame the first floor.

2

10

 

Build the second floor.

2

10

 

Frame the second floor.

3

15

 

Sheath the house.

3

12

 

Install windows and doors.

4

8

 

Install siding.

2

6

 

Put up roof framing.

2

8

Can start as soon as the second floor is framed

Shingle the roof.

1

4

 

Install plumbing.

4

8

Can start as soon as the roof is shingled

Inspect the plumbing.

1

0

 

Install wiring.

6

12

Can start as soon as the roof is shingled

Inspect the wiring.

1

0

 

Hang and finish sheetrock.

4

12

Can start only after the plumbing and electrical work are inspected

Paint the interior.

3

9

 

Lay the carpet.

2

6

 

Install the hardwood flooring.

3

6

 

Install trim.

3

6

 

Procure the certificate of occupancy.

5

0

 

Total

75

184

 

Just as your crew starts framing the second floor, the Smiths tell you that they would now like the additional wing in the house they mentioned previously. The Smiths present you with a new set of blueprints, containing the new wing and ask for a projected difference in price and time for the addition.You figure that to add the extra wing the following would be required in terms of duration and effort:

Task

Duration (days)

Effort (staff days)

Comments

Dig the foundation and footings.

2

6

 

Install forms.

2

6

 

Pour concrete.

1

3

 

Wait for the concrete to harden.

5

0

This is referred to as lag time

Remove forms.

1

2

 

Build the floor.

1

4

 

Frame the first floor.

1

4

 

Build the second floor.

1

4

 

Frame the second floor.

2

8

 

Sheath the house.

2

6

 

Install windows and doors.

2

4

 

Install siding.

1

3

 

Put up roof framing.

2

6

 

Shingle the roof.

1

3

 

Install plumbing.

2

4

 

Inspect the plumbing.

     

Install wiring.

2

4

 

Inspect the wiring.

     

Hang and finish sheetrock.

2

6

 

Paint the interior.

1

3

 

Lay the carpet.

2

4

 

Install the hardwood flooring.

     

Install trim.

1

3

 
       

Total

34

83

 

This new estimate to add the wing, assumes the sheathing will go on the base house and then work will stop until the extra wing is sheathed. You believe this will be the most economical way to add the additional wing to the property. Another option would be for the project to continue as originally planned, and then add the wing after the Smiths have moved in. After considering both options, the Smiths choose to follow your recommendation to add the new wing now so that they move in when the whole house is complete. The additional work required is as follows:

Task

Duration (days)

Effort (staff days)

Comments

Procure the building permit.

5

1

 

Dig the foundation and footings.

2

6

 

Install forms.

2

6

 

Pour concrete.

1

3

 

Wait for the concrete to harden.

5

0

 

Remove forms.

1

2

 

Build the floor.

1.5

6

 

Frame the first floor.

1.5

6

 

Build the second floor.

1.5

6

 

Frame the second floor.

2

8

 

Add the sheath.

2

6

 

Install windows and doors.

2

4

 

Install the siding.

1

3

 

Put up roof framing.

2.5

7

 

Shingle the roof.

1

3

 

Install plumbing.

2

4

 

Inspect the plumbing.

1

0

 

Install wiring.

2

4

 

Inspect the wiring.

1

0

 

Hang and finish sheetrock.

2

6

 

Paint the interior.

1

3

 

Lay the carpet.

2

4

 

Install trim.

1

3

 
       

Total

38

90

 

The rates for the various trades (in $/hour) are as follows:

Code

Description

Rate

Comments

GC

General contractor

40.00

 

HE

Heavy-equipment operator

50.00

Includes equipment

C

Concrete worker

30.00

 

F

Framer

20.00

 

F

Siding installer

20.00

 

W

Window/door installer

30.00

 

R

Roofer

20.00

 

P

Painter

20.00

 

E

Electrician

35.00

 

FL

Flooring installer

20.00

 

T

Trim carpenter

35.00

 

PL

Plumber

35.00

 

In this project, you will analyse the situation and the effect of the change request on the schedule, cost, and features. 

Reference no: EM13305812

Questions Cloud

Faith seeking understanding : Identify clearly the topic(s) you have chosen to discuss and discuss the topic in light of the teachings of the Church
How many days will the fish hatchery have to contain water : If for parathion, the activation energy is 15.4 kcal/mole and A = 8.1 x 109 at a pH = 7.8, how many days will the fish hatchery have to contain the river water if T = 15 oC (winter time)
Determine what is the required pipe size to deliver : A concrete pipeline is installed to deliver 6m^3/sec of water (10degressC) between two reservoirs 17 km apart. If the elevation difference between the two reservoirs is 12m, what is the required pipe size
Find is it virtual or real : A 2.0cm tall object is located 18.0cm in front of a converging lens with a focal length of 10.0cm. Is it virtual or real
Situation and the effect of the change request : The situation and the effect of the change request on the schedule, cost, and features.
How to calculate the forces in members ec and ef : Using method of joints, calculate the forces in members EC and EF. Note that the length of the member CD is 3.464 m, the length of member EC is 2m, and angle CDE is 30 degree ( this will cut down a bit of trigonometry effort).
What price must the division charge in order to break even : The division has fixed costs of $10,000 per month, and it expects to sell 42,000 strips per month. If the variable cost per strip is $2.00, what price must the division charge in order to break even?
What is jaster market / book ratio : It has 800 million shares of common stock outstanding,and its stock price is $32 per share. What is Jaster'smarket /book ratio?
How close will the particles get to each other : A proton is fired directly at a lithium nucleus. If the protonâ€TMs velocity is 4.0x105 m/s when it is far from the nucleus, how close will the particles get to each other

Reviews

Write a Review

Management Theories Questions & Answers

  Types of power according to french & raven

Question: There are 7 types of power according to French & Raven. Which types of power are not necessarily tied to a person's position? Explain briefly!!

  Contrast advantages and disadvantages on just-in-learning

Describe your personal experiences with just-in-time learning. Reflect on a job interview or evaluation where you felt that you were unfairly treated.

  Performance management systems and motivation

I900: Performance Management Systems and Motivation  please 1000 words,  Write a 2- to 3- page critical analysis on the effects of performance management systems on employee motivation. Your analysis should include:

  Conflict between manufacturing and sales

1.  Using the concepts learned in this chapter; analyze the nature of the conflict between manufacturing and sales. Try to identify the sources of conflict and ascertain how far the conflict has gone.

  Prepare a swot analysis

Identify any organization with which you are familiar and provide a SWOT analysis.

  Identify risk management issue of crowd management

Identify risk management issue of Crowd Management

  Analyse the e-commerce

Analyse the e-Commerce and/or e-Business activities in your assigned organisation/industry with the goals found below -  Prepare a 4000-4500 word report (10-11 pages, A4) based upon the organisation/industry sector that has been assigned by th..

  In the allocation of marks

As an external consultant, you have been hired by Overstock.com to evaluate the effectiveness of the processes they undertook in implementing its ERP system and to present your evaluation in report format to the CEO Patrick Byrne.

  The proliferation of new york skyscrapers

Anyone can purchase TDRs. What steps could a person (or a group) who is concerned about the proliferation of New York skyscrapers take to moderate the development of the skyline? How would such groups affect the market for air space rights?

  Strategies for effective group communication

What are strategies for effective group communication during meetings?

  Briefly identify two consequences

The changing workforce is one of the emerging trends in organizational behavior. Describe how the workforce is changing and briefly identify two consequences of these changes for organization

  How material can be applied to managerial decision making

How the material can be applied to managerial decision making and the implications for improving managerial decision making

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd