Show this operation on a linear schedule

Assignment Help Civil Engineering
Reference no: EM13564904

A project consists of replacing the track on an existing railroad line, involving 3000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be removed at a rate of 200 feet (measured along the track) per hour. The new ties can be installed at a rate of 25 feet per hour and the replacement track can be installed at a rate of 40 feet per hour. Show this operation on a linear schedule. Assume that the minimum float for an activity at any location is one day.

Reference no: EM13564904

Questions Cloud

Determine the improvement in efficiency and circulation rate : Now you want to improve the efficiency and circulation rate. You suggest operaing the cycle utilizing two reversible tubines with saturated vapor exit streams. All conditions remain the same except that the feed to the first turbine is steam at 450 C..
Estimate the flow rate of water required to make the outflow : A mixing chamber has two steady streams and one steady stream. The properties of the first stream is superheated steam at T1 = 400oF, h1 = 1,239 Btu/lbm and flow rate m1 = 20 lbm/h. The second stream is compressed liquid at T2 = 70oF, h2 = 38 Btu/lbm..
Determine the volume flow rate of the steam at the nozzle : A steady-state, well-insulated turbine operates in two stages in series using steam. the first stage has an efficiency of 85% and the second stage 90%. Steam enters the first stage at 400 C and 4 MPa and exits at 1.5 MPa.
Determine the volume flow rate for this particular water : Everyone has experienced using a water fountain that produces a bit too much water pressure. In fact, the drinking fountain on the 3rd floor of Dana Hall at the south end of the hallway shoots a pretty good jet of water
Show this operation on a linear schedule : A project consists of replacing the track on an existing railroad line, involving 3000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be removed at a rate of 200 feet (measured along the track) pe..
What is the project duration if no activities are to be : A 1500-foot subdivision street is to be constructed. The layout will be completed in three days; the fill will be brought in over the course of eight days; the compaction/grading will be completed in five days
Find the effective angle of shearing resistance of sand : An adiabatic compressor is used to bring saturated water vapor at a pressure of 103 lbf/in^2 up to 1000 lbf/in^2, where the actual exit temperatureis 1000 F. Find the compressor fficiency an the entropy generation. Is there a improvement by reducing ..
Estimate the angle through which the part rotates : A machine part rotates at an angular speed of 0.60 rad/s; itsspeed is then increased to 2.2 rad/s at an angular acceletation of0.70 rad/s2
What is the increase in tempterature of the water : The apparatus show in firgure P11.8 was used by Joule tomeasure the mechanical equivalent of heat. what is the increase in tempterature of the water

Reviews

Write a Review

Civil Engineering Questions & Answers

  Assume that the player strikes the cue ball so that it

in eight ball a player needs to pocket the eight ball to win the game. assume that the player strikes the cue ball so

  What is the emission rate of carbon tetrachloride from this

A dry cleaning establishment buys 500 gal of carbon tetrachloride every month. as a result of the dry cleaning operation, most of this is lost to the atmosphere and only 50 gal remain to be disposed of.

  What is the concentration of the chemical in the water

25 mg chemical Y (log kow = 2.88) is added to a microcosm (i.e., tank) that contains 1 kg soil, 20 L water. Chemical Y has negligible volatility (very low partitioning to air). The soil is mized with water for several days until equilibrium (between ..

  What is h2co3-hco3-co3 2 and partial pressure of co2

The total dissolved inorganic carbon (TIC) of a sample of groundwater is 8.33 mM. The temperature of the aquifer is 15C, the pH is 7.5, and the ionic strength is 0.05 M. What is the H2CO3, HCO3-, CO3 2-, and the partial pressure of CO2

  Determine moment of inertia of beams cross-sectional area

Determine the moment of inertia of the beam's cross-sectional area about the x-axis. Set a = 40mm , b = 130mm , d = 110mm , h = 380mm .

  Determine the normal depth in the channel for a discharge

If you have 10 kips acting downward on a foundation and footing, 4 feet long, with uniformly distributed load acting up ward of 2.5 k/ft (soil) also 4 ft long. what are the reactions, shear forces, and bending moments at the tree critical points?

  A layer of clay 4m thick lies between two layers of sand

a layer of clay 4m thick lies between two layers of sand each 4m thick the top of thenbspupper layer of sand being

  Find x-y and z coordinates of point b for radial readings

calculate the X, Y and Z coordinates of point B for radial readings taken to B from occupied station A, if the backsight azimuth at A is 25°32'48", the elevation of A = 610.098 m, and hi = 1.45 m.

  Which would mean that an embankment is in saturated

Total stress analysis is usually preferred for construction of embankments and for excavations, we use effective stress analysis, but why? Total stress is Undrained strength of the soil

  Determine the exit pressure and power required

Air enters adiobatic compressor at 100kpa, 20 degrees celcius at rate of 0.1 kg/s and exits at 200 degrees celcious. compressor efficiency is 70%. Determine the exit pressure and power required.

  Determine the net power output of the engine

The cycle has a thermal efficiency of 35%, and steam changes from saturated vapor at 300 C during the heat addition process. If the mass flow rate of the steam is 2kg/s, determine the net power (kw) output of this engine.

  Determine the flow discharge in the canal

A trapezoidal canal with a bottom width of 1.5m, a side slope Z=1, has a longitudinal slope of 0.4% and n=0.025. If the water depth in section 1 is 1.52 m and in section

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd