On January 2, Wabash Construction Company, a general contractor, executed a written contract with Anderson Brick, Inc., a subcontractor. The contract relates to a major “strip mall” building project in Morgantown, and Wabash faces a deadline of October 31 in its contract with The Mackie Consortium, L.L.C., the owners of the new mall. In the agreement between Wabash and Anderson, the parties stipulate that “time is of the essence” in terms of performance of the bricklaying work, and that the deadline for Anderson’s completion of the bricklaying work is July 15. There is also a “liquidated damages” clause in the contract between Wabash and Anderson, indicating that if the work is not completed by July 15, Anderson will pay $2,000 in damages for every day the bricklaying is not completed beyond July 15.
Anderson does not complete the bricklaying work by July 15. In fact, the project is not finished until August 30, and Wabash now claims liquidated damages from Anderson in the amount of $92,000 (representing 46 days beyond the July 15 deadline, multiplied by $2,000 per day.) Anderson refuses to pay the $92,000, and Wabash sues.
At trial, Anderson’s attorney seeks to introduce the following evidence: 1) the testimony of Henry Anderson, Anderson’s owner, who is willing to testify under oath that at the time of the signing of the contract, Wabash’s general manager, Fred Stein, said “Pay no attention to the July 15 deadline in the contract; if you need more time, all you have to do is ask;” and 2) a crumpled index card, purportedly in Fred Stein’s handwriting, indicating “no ‘hard and fast’ deadline on Anderson brick work.”
Should the trial court judge admit the foregoing evidence?
Identify basic concepts of influence and power
: Examine different group and team concepts as they relate to performance and diversity. Identify basic concepts of influence and power. Discuss Fiedlers Contingency Theory and Discuss Path-Goal Theory
|
What will be the resulting equilibrium
: Suppose the network managers meet to coordinate schedules and Network 1 promises to schedule its big show first. Is this promise credible? What would be the likely outcome?
|
What expenditures mr schultz should include and total them
: Mr. Schultz is uncertain about what other expenditures in relation to this purchase he should include in the cost of land. From the following list, choose what expenditures Mr. Schultz should include and total them.
|
What are the key internal controls
: What are the key internal controls
|
Should the trial court judge admit the foregoing evidence
: On January 2, Wabash Construction Company, a general contractor, executed a written contract with Anderson Brick, Inc., a subcontractor. The contract relates to a major “strip mall” building project in Morgantown, and Wabash faces a deadline of Octob..
|
Agreed to build a home for maggie sykes
: Hillman Brothers Construction, Inc. agreed to build a home for Maggie Sykes. The total contract price for the home is $325,000. The home is complete in all respects except for the fact that shutters have not been installed on the windows.
|
Which firm will spend more to speed up its planning
: Suppose that both firms try to maximize profits, but that Firm A has a head start in planning and can commit first. Now what will be the outcome? What will be the outcome if Firm B has the head start in planning and can commit first?
|
Edition of the atlantic monthly
: In the October 1995 edition of The Atlantic Monthly, Cobb, Halstead, and Rowe, offer a look at the deceptive nature of citing growth based upon the GDP as an indicator of our well-being. How is the GDP an inadequate measure of the nations health a..
|
What do profitability ratios indicate about the company?
: What do profitability ratios indicate about the company?
|