Shortest time to complete a network

Assignment Help Basic Computer Science
Reference no: EM13951334

1. When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration.

2. AON and AOA networks can both be used to depict any project network.

3. The shortest time to complete a network is equal to the duration of the longest path through the network.

4. Critical path tasks always have zero slack.

5. To manage a project successfully, the project manager need only pay close attention to tasks on the critical path.

6. "Merger" is a term used to describe the situation in which two or more paths in a network join together.

7. If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.

8. The actual project duration will be known with certainty after the project is completed.

9. Milestones cannot be identified on a Gantt Chart.

10. It is easiest to see lead and lag time in a project task on a PERT/CPM networks.

11. A start-to-finish linkage is the most common way of linking to successive task.

12. The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a Beta distribution.

13. A project schedule is a project action plan converted into a timetable.

14. A Gantt chart can NOT depict a critical path, only a PERT/CPM chart can.

15. The difference between the LST and EST is called slack.

16. A disadvantage of Gantt charts is that they are hard to draw.

17. The difference between LST and LFT is called slack.

18. Standard Pert/CPM networks can be use to resolve probabilistic concerns

19. Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.

20. The difference between EST and LFT is called slack.

21. The difference between LFT and EFT is called slack.

22. A big advantage of AON networks is that they are easier to draw.

 

23. The tasks of project planning, project budgeting, and project scheduling are largely separable from one another.

24. An event is a series of connected activities.

25. A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.

26. The simulation approach is generally preferred over the statistical method.

27. Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks.

28. The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.

29. Milestones are not depended upon the predecessor activities in the project plan.

30. Another name for total slack is free slack.

31. What is it a milestone?

32. What is project slack?

33. For which purpose is simulation NOT used with regard to project scheduling?

34. Technical dependencies on a project plan are easiest to see on a:

35. PERT was originally used for what type of project?

36. Which of the following is NOT an element of the Gantt chart?

37. Which of the following is typically used as the best estimate of task duration?

38. Which of the following terms is most closely associated with a task required by the project?

39. What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?

40. What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively assuming the estimates were made at the 99% plus level?

41. The amount of time a noncritical task can be delayed without delaying the project is called?

42. Slack is calculated as?

43. Which of the following linkages is used to start two or more activities at the same time?

44. A Term NOT used in the discussion of PERT/CPM analysis is

45. An identifiable state resulting from the completion of one or more activities is called?

46. Define the term Critical Path.

47. What is activity slack?

48. What is a Gantt chart?

49. What are the four methods of linking steps in a project using precedence diagramming?

50. Contrast "total slack" and "free slack"

51. Contrast the traditional statistical approach to calculating the probability of completing a project by a specified time with the simulation approach.

52. Why should we only draw the Gantt chart after we have draw the network for the project?

53. What assumptions are made about the probabilities of the optimistic and pessimistic times in the standard formula for calculating the variance of a particular activity? Explain how the formula can be modified to accommodate different assumptions.

54. Explain why the term "critical path" has less meaning in cases where the activity times are not known with certainty.

55. What is a merger and what problems do mergers create?

Why is it necessary for the PM to be aware and to manage the slack in the project?

Reference no: EM13951334

Questions Cloud

Find velocity of your feet, v, due to the rotation of earth : Find the velocity of your feet, v, due to the rotation of Earth. Assume that Earth is a perfect sphere of radius R=6378km and that a day is exactly 24 hours long.
Important things for a leader to posses : The textbook states that self-awareness is the number one most important things for a leader to posses (Daft, 2014 p.454). I can see how understanding yourself is important because you can recognize differences in personality traits, emotions, and..
Do you have any security concerns for using virtual networks : Virtualization has become a key player in our networking world these days. Another important term is the virtual private network (VPN). Are the two terms (virtualization and VPN) related? Discuss and give examples. Do you have any security concern..
How long would it take for a radio wave to travel : How much heat that must be added to raise the temperature of a cup of coffee (250g) from 25.5ºC to 95.6ºC. Assume that the coffee has a specific heat of 4.187 ?
Shortest time to complete a network : If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.
How could bob and alice mitigate this situation? : If so, how could she do it, and would Bob or Alice know that Eve was reading their messages? How could Bob and Alice mitigate this situation?
What minimum barrier thickness is there no reflection : A H2 molecule can be approximated by a simple harmonic oscillator having a spring constant k = 1.1 ? 103 N/m. How many different energy transitions are possible when the H2 molecule decays from the third excited state down to the ground state?
Work in process inventory, and cost of goods sold : Prepare a journal entry to close the variance accounts at Bell Computers. Assume that the total variance is material and is apportioned among Finished Goods Inventory, Work in Process Inventory, and Cost of Goods Sold.
Challenges in the global business environment : According to the textbook, ongoing challenges in the global business environment are mostly attributed to unethical business practices, failure to embrace technology advancements, and stiff competition among

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd