Scenario analysis for mutually exclusive projects

Assignment Help Finance Basics
Reference no: EM1329767

Basic scenario analysis Murdock Paints is in the process of evaluating two mutually exclusive additions to its processing capacity. The firm's financial analysts have developed pessimistic, most likely, and optimistic estimates of the annual cash inflows associated with each project.

Project A Project B
Initial investment (CF0) $8,000 $8,000
Outcome Annual cash inflows (CF)
Pessimistic $ 200 $ 900
Most likely 1,000 1,000
Optimistic 1,800 1,100

a. Determine the range of annual cash inflows for each of the two projects.

b. Assume that the firm's cost of capital is 10% and that both projects have 20-year lives. Construct a table similar to this for the NPVs for each project. Include the range of NPVs for each project.

c. Do parts a and b provide consistent views of the two projects? Explain.

d. Which project do you recommend? Why?

Reference no: EM1329767

Questions Cloud

Explain customer service challenges for e-commerce : Explain Customer Service challenges for e-commerce and Discuss the main challenges that e-commerce organizations face in the customer services arena
Strengths and weaknesses of personal selling : Show the strengths and weaknesses of personal selling, and describe a situation in which a company could benefit from including personal selling strategies in its IMC plan.
Explain analyze the supply chain of home depot and lowe''s : Explain Analyze the Supply Chain of Home Depot and Lowe's and Explain how the supply chain was modified form brick to mortar by e-commerce
Turning sustainability shortcomings : Identify ways in which it may expand upon current or past sustainability successes and Identify opportunities for turning sustainability shortcomings into areas of sustainability growth.
Scenario analysis for mutually exclusive projects : Find out the range of annual cash inflows for each of the two projects. Suppose that the firm's cost of capital is 10% and that both projects have 20-year lives. Develop a table similar to this for NPVs for each project. Comprise the range of NPVs ..
Explain project management- project success or failure : Explain Project Management- identify factors that contribute to project success or failure and include recommendations as appropriate
Negatives aspects of establishing crm : Customer Relationship Management explained in this answer - Can you help me with this assignment?
Explain impact of three changes brought about by e-business : Explain Impact of three changes brought about by E-Business and assesses the impact of three changes brought about by E-Business
Annuity payment amounts with changing interest : Set up the fund of semi-annual payments to be compounded semi-annually to accumulate the some of $100,000 after 10 years at 8 percent annual rate (20 payments). Find out how much the semi-annual payment should be. (round to whole numbers.)

Reviews

Write a Review

Finance Basics Questions & Answers

  Objective type questions on cost of capital

Objective type questions on cost of capital and capital budgeting and rule states that a typical investment project with an IRR that is less than the required rate should be accepted

  Find the capital structure components and computation

Capital Structure components and computation with before and after tax cost of capital - Theory and What sources of capital should be included when you estimate Coleman's WACC?

  Sovereign mines investment analysis

Sovereign Mines Investment Analysis

  State pricing theory and no-arbitrage pricing theory

State pricing theory and no-arbitrage pricing theory

  Computation of yield to maturity when interest is paid

Computation of yield to maturity when interest is paid and compounded annually and bond's rate of return earned

  Computation of value of the and calculate for each bond

Computation of value of the bond and Calculate for each bond the percentage price change associated with a change of yield to maturity

  Computation of pv and future annual payments

Computation of PV and Future Annual Payments and principal amount and Compute the original principal amount

  Find out the standard deviation of returns over this iod

Find out the variance of returns over this each iod. Find out the standard deviation of returns over this each iod.

  Computation of rate of inflation with given data

Computation of rate of inflation with given data and what does the market anticipate will be the rate of inflation three years from now

  Describe identification of audit errors made by em

Describe Identification of Audit Errors made by EM and Precautionary measures to be taken and There were several unusually large sales that were made near year end

  Time value of money-questions

Find out the amount that should be deposited now at compound interest to provide the desired sum for each of the following:

  Ratio analysis and assets and liability classifications

Ratio analysis, assets and liability classifications, revenue and expenses reporting, basis and calculations for accrual basis accounting and reporting and Basic earnings per share is evaluated

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd