1. What are the two pass processes to determine the time schedule?
a. Forward and Backward Pass
b. Lateral and Remedial Pass
c. Reverse and Normal Pass
d. Work Activity and Migration Pass
2. Gantt chart helps project managers to do which of the following?
a. Activities are planned
b. Order of performance is documented
c. Activity time estimates are recorded
d. Overall project timeline is developed
e. All the above
3. What is the method of measuring random samples of batches against predetermined standards?
a. Process Capability Analysis
b. Acceptance Sampling
c. Population Sampling
d. Acceptance Criteria
4. The process where we shorten the duration of a project in the cheapest manner possible.
a. Project minimization
b. Project crashing
c. Project leaking
d. Project alignment
5. Which is not a reason for the importance of project management in an organization?
a. Managing projects can be challenging for Operations Managers
b. Can result in cost overruns
c. Can be controlled by careful monitoring of progress
d. Prevent delays