Revised project management plan and report to management

Assignment Help Project Management
Reference no: EM13869173

Question 1

Developing a Revised Project Management Plan and Report to Management

Background

You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:

  • Consultant
  • Government organisation
  • Construction company
  • Installation company
  • Asset management provider
  • Maintenance services provider
  • Other.

The organisation may be operating in one or more engineering disciplines, such as civil, mechanical, electrical, environmental, mechatronic, biomedical, or other discipline, or in construction or surveying.

Your organisation has asked you to review the management of a medium sized project (up to $5 million in value), which is to be completed within two (2) years of its commencement. The project has at least 20 main activities and at least two (2) critical paths.

The project commenced eight (8) months ago. The first six (6) weeks were spent developing the project charter and preparing the original project management plan. Project execution (carrying out the work) commenced immediately the project management plan was completed and approved.

There will be a one (1) month project closing period at the end of the project. During this time, equipment will be tested and commissioned (if relevant to your project), and the project will be finalised.

The project deadline is firm, subject to any justifiable contingencies.

The existing business case and project charter are not detailed. Similarly, the project management plan, including a basic Gantt chart and high level budget is not well detailed or described.

There are a number of issues with the project:

1. To date, the project is two (2) months behind schedule. Part of this delay has resulted from poor understanding of lead times for delivery of particular project components. There are no other significant factors that should impact on project delivery.

2. Because there is only a quite basic project plan and time schedule, there is poor sequencing of critical activities. They do not have clear scheduled completion dates.

3. There have been delays in procuring some critical project resources. There may be alternative suppliers.

4. While there were a number of specialised personnel for particular aspects of the project available at the start of the project, they were not booked ahead of when they were required. Most of these resources are now booked for several months ahead. Few alternatives are available.

5. As a result of the influence of a number of stakeholders, there has been significant scope creep, which with the current rate of progress will delay delivery by one (1) month. This scope creep also threatens to impact on the project's business case.

6. Some components of the project have not been delivered or built to the required quality specification. Consequently, there have been delays while defects have been rectified.

7. Communication between project manager, project sponsor, stakeholders, contractors, consultants and other key personnel has not been good. There are therefore a number of cases where key information has not been communicated well. This poor communication has impacted on project progress.

You have been charged with delivering a revised project management plan to deliver the project on time; and with providing a report to the Project Sponsor explaining the actions you have taken.

Your Task

Part A

1. Define  your  organisation and project.

Nominate an organisation of your choice, and the engineering discipline or disciplines in which it is operating.

Nominate a suitable project (for example, road development, subdivisional development, power station, mobile phone network, mining, provision of industrial equipment, installation, maintenance, surveying) to use as an example.

2. Prepare a revised project charter, including an updated  business plan.

3. Prepare an updated project management plan for completing the project within its original timeline.

The project management plan should include the following:

  • Definition, preparation and definition of subsidiary plans
  • Identification and description of stakeholder needs
  • Work Breakdown Structure (WBS)
  • Plans for the project management Knowledge Areas of:
  • project integration management
  • project scope management
  • project time management
  • project cost management
  • project quality management
  • project human resource management
  • project communications management
  • project procurement management
  • Definition and sequencing of the main project activities
  • Main activity resources and durations
  • Project schedule, costs and budget Notes:
  • The project charter should include a revised business case for the project and link the project with your organisation's strategic plan. On the basis of this business case, the project sponsor will make a decision about the future of the project.
  • You may assume that the project sponsor has allowed the project timeline to be increased by one (1) month to allow for the scope creep already approved. However, further scope creep is not permitted.
  • The project scope management plan should include a section on controlling scope creep
  • The project time management plan should include a Gantt chart showing the major project activities.
  • The project cost management plan should include all costs reasonably expected to be incurred in delivering the project. These costs may include estimates for ensuring completion of the project.

4. Prepare a plan for executing, monitoring and controlling  the project

5. Prepare a plan for any testing and commissioning, and for closing the project

Part B

Write a report to your Project Sponsor that:

  • succinctly outlines the steps you have taken to deliver the project within its original timeframe (as extended by permitted scope creep of one (1) month)
  • explains why they have been taken
  • demonstrates how they will enable the project to be completed within its original timeframe
  • discusses the additional costs that will be incurred to achieve this target

Part C (Written Communication)

Abstract  and  table of contents

Structure

Language,  style,  spelling

Completion in  within word count

Setting  out and referencing

Reference no: EM13869173

Questions Cloud

Design and implement a simulation of the game of volleyball : Design and implement a simulation of the game of volleyball. Normal volleyball is played like racquetball, in that a team can only score points when it is serving.
Substance a disappears following zero order : Substance A disappears following zero order kinetics with rate constant as 0.015 M s-1. Estimate the concentrationof A left after 25 seconds if the initial concentration is 0.5 M ? A first order reaction has half-life 10 min. If the reaction is start..
Explain entire marketing plan of action for chosen product : You are to select a tangible product that exists in the marketplace, not a service and create or explain the entire marketing plan of action for your chosen product, including the Four-Ps of marketing or all of the elements of the Marketing Mix
Specific industry guidance under u.s. gaap or ifrs : If a motion picture company wanted to find specific guidance on how to recognize revenue related to its film licensing rights,
Revised project management plan and report to management : You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:
Draw the tree graph for tictactoe game : draw the tree/graph for this file (circles as nodes and lines from parents to children). The board positions in the nodes are real. The weights are not what would be in the real game
Determination of molecular weight by freezing point : Describe the determination of molecular weight by freezing point depression method. Write a proper descritipn of given topic along with proper refrences.
Perform a finite element analysis on a mechanical system : The purpose of this project is to perform a finite element analysis on a mechanical system in ANSYS and communicate the results clearly in a standard report format.
What types of risk do you think affects each of investment : What types of risk do you think affects each of the investments?

Reviews

Write a Review

Project Management Questions & Answers

  Describe a project in which you are currently

describe a project in which you are currently involved.explain a project in which you are currently involved e.g.

  Prepare the case for an optimistic sales manager

Prepare the case for an optimistic sales manager who suggests that you should move ahead with the FMS now

  Individual assignment leadership and transformation an

individual assignment leadership and transformation an important aspect of a graduate education is the ability to

  Part-1question1compare and contrast the ideas of semantic

part-1question1compare and contrast the ideas of semantic complexity and structural complexity of a computer program.

  How does organizational culture influence the selection

Show how does organizational culture influence the selection, sponsorship, prioritization, and ultimate success of projects and in what ways could organizational culture create conditions that could lead to the scenario described above?

  Total carrying cost per yearif it costs 2 in storage costs

total carrying cost per yearif it costs 2 in storage costs to hold a 10 item in storage for 1 year the total carrying

  Designing evaluation form used by functional employees

Design an evaluation form to be used by functional employees after project termination to evaluate the effectiveness of the project manager.

  What problem-solving steps should raymond apply

What problem-solving steps should Raymond apply in this situation? How will the use of problem-solving steps impact his business?

  Explain how should a project manager handle a situation

Explain how should a project manager handle a situation in which the functional manager or employee appears to have more loyalty to his profession, discipline, or expertise than to the project

  The product safety issue that led to the lawsuit

Describe the company and the product safety issue that led to the lawsuit.

  Characteristics or attitudes of a project manager

Explain with anecdotal evidence your top three qualities as project manager. Identify and explain three characteristics/attitudes of a project manager that may lead to project failure

  Project termination and management

Project Termination and Management - explain what is the significance of the termination checklist? When should it be developed

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd