Reference no: EM13741573
All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT:
reviewing project documents
documenting lessons learned
interviewing stakeholders
brainstorming among team members and subject matter experts
4 points
Question 2
All of the following criteria can be used to categorize project risks EXCEPT:
whether the risk is a known risk
the project objective that may be impacted by the risk
whether the risk is internal or external to the performing organization
the project life cycle phase
4 points
Question 3
All of the following are among the activities a project manager should undertake to develop a highly effective team EXCEPT:
assess sponsor capability
assess project team capability
establish team ground rules
assess individual member capability
4 points
Question 4
A description of the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services or results is known as:
the contract clauses and special provisions
the procurement statement of work
the supply invoice
the purchase order
4 points
Question 5
Which of the following quality management thought leaders is generally credited with contributing the insight that team learning is necessary to improve quality?
Ishikawa
Senge
Taguchi
Harrington
4 points
Question 6
It is argued that project teams progress through five stages of team development. Which of the following sequences best represents this progression?
forming, norming, storming, performing, reforming
forming, storming, norming, performing, adjourning
forming, storming, norming, performing, reforming
forming, performing, reforming, norming, adjourning
4 points
Question 7
Which estimating technique uses historical data from a similar project as a starting point for creating a time or cost estimate?
analogous estimating
parametric estimating
bottom-up estimating
Monte Carlo estimating
4 points
Question 8
The Validate Scope process occurs with interim deliverables throughout the project and with final deliverables near the end.
True
False
4 points
Question 9
All of the following accurately describe skills that an owner's representative can use during the project when making tradeoffs EXCEPT:
Managing change
Inspecting quality into the project
Team building
Knowledge of criteria
4 points
Question 10
Change control includes which of the following activities?
identifying, documenting, approving or rejecting, modifications to documents, deliverables, or baselines
brainstorming, selecting and implementing new ideas
recruiting, selecting and training new team members
identifying and implementing changes to the project charter
4 points
Question 11
Which of the following statements is consistent with the ideas that W. Edwards Deming promoted regarding quality management?
Understanding variation is essential to improving quality.
Statistical concepts rather than behavioral considerations should govern quality improvement efforts.
The burden of quality falls on those that do the work
A key to quality improvement is to ensure that each part of the system functions effectively, independent from the others.
4 points
Question 12
What type of cost is incurred when a project must be conducted faster than normal, and overtime for workers and / or extra charges for rapid delivery from suppliers are necessary?
marginal costs
expedited costs
nonrecurring costs
variable costs.
4 points
Question 13
The decision process for developing relevant quality standards on a project includes all of the following activities EXCEPT:
identify all stakeholders
understand the prioritized stakeholders' requirements
design work systems
make tradeoff decisions
4 points
Question 14
Joseph Juran provided guidance regarding how to control quality. Which of the following items is consistent with his quality control guidance?
identify all team members and their needs
establish measurement systems
prove effects
expend necessary efforts to exceed requirements
4 points
Question 15
On long projects it is often better to capture lessons frequently since people may not remember clearly what happened several months previously.
True
False
4 points
Question 16
Which estimating technique uses an algorithm to calculate cost or duration based on historical data and other project parameters?
empirical estimating
parametric estimating
grass roots estimating
analogous estimating
4 points
Question 17
DMAIC is a disciplined process that includes five phases: Define, Measure, Analyze, Improve and Control. DMAIC is most typically associated with which of the following quality improvement approaches?
Malcolm Baldrige
Total Quality Management (TQM)
Six Sigma
ISO 9001:2008
4 points
Question 18
On agile projects, detailed risk management activities may occur during all of the following times EXCEPT:
While planning each subsequent iteration.
During early risk planning at the start of the project.
In daily stand-up meetings.
During retrospectives at the end of each iteration.
4 points
Question 19
On some projects, some deliverables remain incomplete at project close-out. Activities that are not complete should be itemized, and responsibility for each should be clearly identified.
True
False
4 points
Question 20
The process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents and project management plan; and communicating their disposition, is known as:
perform project monitoring.
variance analysis and control.
perform integrated change control.
configuration management
4 points
Question 21
All of the following are among the benefits realized as a consequence of developing a cost management plan EXCEPT:
It shows how to develop and share relevant, accurate and timely information that stakeholders can use to make intelligent and ethical decisions.
It documents how the business case should be created
It helps stakeholders to focus on schedule and performance as well as cost.
It provides feedback that shows how the project's success is related to business objectives.
4 points
Question 22
More organizations effectively collect lessons learned than effectively disseminate and use them.
True
False
4 points
Question 23
All of these are factors that could lead to a decision to buy or outsource rather than make or perform in-house, EXCEPT:
flexibility in procurement
ability to use specialized suppliers
inadequate capacity
more control over quality and time
4 points
Question 24
The procurement management plan:
describes how the procurement division will be managed.
describes how supply chain partners will be managed.
describes how a project team will acquire goods and services from outside the performing organization.
describes how sellers will be audited by the procurement team.
4 points
Question 25
Implementing approved changes as directed by the project's integrated change control system.
True
False
4 points
Save and Submit
Click Save and Submit to save and submit. Click Save All Answers to save all answers.
Carefully analyze the poem if we must die by claude mckay
: Carefully analyze the poem If We Must Die by Claude McKay in terms of its themes and its rhetorical strategies. Explain how and why this poem is connected to the works of the vernacular tradition.
|
Enter the formula to compute the percentage change
: Enter the formula to compute the Percentage Change in the CNC row (fourth column) and copy the formula to the other cells in the column. Which retailer's m-commerce site has shown the most change since 2010
|
Why is this disorder continuing to become more prevalent
: According to the National Institute of Mental Health (2015), nearly 30% of American adults will suffer from diagnosed anxiety in their lifetime (with those rates rising each year). Why is this disorder continuing to become more prevalent with each ..
|
Description of three basic types of cells
: A definition of spongin is given. A description of three basic types of cells that make up a sponge is given
|
Reviewing project documents
: All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT:reviewing project documentsdocumenting lessons learned
|
How effective are ngos as compared with ios
: How effective are NGOs, as compared with IOs, that are active in disarmament? Where do NGOs should focus their attention on? Which tools does the UN have to hold violators accountable and seek re-dress? Looking at recent developments on Iran and US r..
|
Compare the role and powers of the office of management
: Compare the role and powers of the Office of Management and Budget to the Congressional Budget Office.
|
Write an essay on crime in american gangs
: Write an essay on Crime in American Gangs. For extra credit, students may write 5 to 10 page papers.
|
How have igos and ngos contributed to preventing
: How have IGOs and NGOs contributed to preventing and containing international nuclear arms races? Further, what role should the UN have in peacekeeping operations within states that violate international treaties against nuclear proliferation?
|