Calculation of Labor Variances.
The following direct materials and labor data pertain to the operations of Solario Manufacturing Company for the month of August.
Costs
Actual labor rate
$13 per hour
Actual material price
$128 per ton
Standard labor rate
$12 per hour
$130 per ton
Quantities
Actual hours incurred and used
4,200 hours
Actual quantity of materials purchases and used
1,225 tons
Standard hours used
4,300 hours
Standard quantity of materials used
1,200 tons
Instructions:
Provide two possible explanations for each of the unfavorable variances calculated in E25-8 (a), and suggest where responsibility for the unfavorable result might be placed. Refer to E25-8 (a).
Evaluate the amount of gross profit recognized by URS throughout each year from 2013 through 2016.
Journalize the adjusting entries and the transactions - Transactions for fixed assets including sale
Calculation of contribution margin per unit - Determine the contribution margin per unit?
Evaluate the gross profits to be identifies for each of the three years. If the outcome of the construction contract can't be reliably estimated, evaluate the gross profit for each year be?
On overseas distributor has expressed an interest in these units if the price is substantially reduced. Evaluate the minimum price that would be acceptable to Redi-Watt in selling these units.
Evaluate the amount to be reported as the cost of the land
Prepare a schedule for each month showing budgeted cash disbursements for the Tilson Company and a schedule for each month showing budgeted cash receipts for Tilson Company
Finding the equivalent units for materials and conversion - Determine the costs per equivalent unit for May?
Applicable Codification references Related presentation and disclosure issues for the notes Any additional clarifying information needed from company management
Journal entries for warranty repairs. - 1. Paid $12,350 for warranty repairs originally accrued in 2008.
Determine the key areas being addressed by the EITF and assess how a company's accounting and financial reporting is likely to be impacted by the work being done by the EITF on this issue.
Purpose a production budget for February, March, and April. and a forecast of the units and cost of raw material that may be required for February, March, and April.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd