Requirement of the progress evaluation techniques

Assignment Help Project Management
Reference no: EM131782690

Task Description

Assignment Overview

This assignment is a group assignment and it includes two parts: Part A and Part B. Each part is explained in detail below:

PART A

Part A of the assessment item requires you to consider:-

• earned value management

You must then analyse a supplied earned value report. The earned value report has been provided to meet the requirements outlined in the PMBOK (2013) and conforms to the requirements of the progress evaluation techniques (p.108) outlined in Managing Successful Projects with PRINCE2 (2009).

Task

Your task is to consider the overview above and analyse the earned value and S-curve report. You will be graded upon how well your analysis of the earned value and S-curve reports have been completed and reflects information based on a case study.

Purpose
The primary purpose of this assessment item is to help you to develop skills in the contents and compilation of earned value and S-curve report.

The secondary purpose of this assignment is to give you the opportunity to consider the role of progress evaluation techniques and control within a project life cycle.

The assignment will also give you the opportunity to enhance your analysis and written communication skills; particularly in the areas of rigorous structured assignment writing.

Structure
Your submission must be made using the supplied earned value report. You should complete all of the required parts of the earned value and S-curve reports in a manner as you deem appropriate. The instruction boxes in the report will provide more information.

PART B
Part B of this assessment item requires you to consider:-
• event-driven controls, and
• time-driven controls

You must then analyse the items listed above for the supplied case study. A template for the controls report has been provided to meet the requirements outlined in the PMBOK (2013) and conform to the progress and project control requirements outlined in Managing Successful Projects with PRINCE2 (2009).

Task
Your task is to consider the overview above and develop and complete the required items in the report. You will be graded upon how well your submissions have been completed and reflect the case study.

Purpose
The primary purpose of this assessment item is to help you to develop skills in the definition and development of event and time driven management processes.

The secondary purpose of this assignment is to give you the opportunity to consider progress and project control requirements within a project life cycle.

The assignment will also give you the opportunity to enhance your analysis and written communication skills; particularly in the areas of structured assignment writing.

Structure
Your submission should be made using the supplied case study and controls report template. You should complete all of the required parts in as complete manner as you deem appropriate. The instruction boxes in the report will provide more information.

Reference no: EM131782690

Questions Cloud

Estimate the true mean number of meals : A survey of 20 couples showed the mean number of meals eaten outside the home was 2.76 per week and the standard deviation was 0.75.
How many tours must be sold to break even : Canyon Escape sells individual tickets for $75 for walking tours of the Grand Canyon. How many tours must be sold to break even
Calculate the maintenance cost : Calculate the maintenance cost that would be budgeted for the month of May in which 5,700 machine hours are planned to be used
Why should bell company make or buy the subassembly : PROBLEM- MAKE OR BUY DECISION. Why Should Bell Company make or buy the subassembly? Support your answer with analysis.
Requirement of the progress evaluation techniques : Analyse a supplied earned value report. The earned value report has been provided to meet the requirements outlined in the PMBOK (2013)
Calculate the annual cash dividends to be paid : Calculate the annual cash dividends to be paid for each of these preferred stock issuances: $2.40 cumulative preferred
Calculate cypress corporations alternative tax liability : Calculate Cypress Corporation's alternative minimum tax liability. Assume Cypress Corporation is not a "small corporation" for AMT purposes.
What is the rebate expense and liability : What is the rebate expense and liability, respectively, shown on the 2007 financial statements dated December 31
In what year would the total expenditures reach given target : In what year would the total expenditures reach $222 million dollars? If this model remains accurate, when would the total expenditures reach $493 million?

Reviews

len1782690

12/26/2017 7:20:55 AM

Your submission should be made using the supplied case study and controls report template. You should complete all of the required parts in as complete manner as you deem appropriate. The instruction boxes in the report will provide more information. ________________________________________ Weighting 30% ________________________________________ Assessment Criteria Your assignment will be assessed on the extent and quality to which it meets each of the following criteria. • A complete and correct analysis of the earned value report? (40%) A complete and correct analysis of the controls report? (40%) Appropriate and well structured, concise and clear expression of project management arguments in response to the assessment task? (10%) Clarity of expression, grammar and spelling? (10%) Referencing Style Harvard (author-date) Submission Online Group Learning Outcomes Assessed Define and justify project event-driven and time-driven controls for a case study project Graduate Attributes Cognitive, technical and creative skills Research Ethical and Professional Responsibility

Write a Review

Project Management Questions & Answers

  What is the kinetic energy of the main part

(a) What is the total mechanical energy of the roller coaster/earth system at the 40m hilltop? (b) What is the kinetic energy of the roller coaster at the 5m dip? (c) What is the kinetic energy of the main part of the roller coaster at the 30m crest ..

  Computing reduce solid office waste volume

Reduce solid office waste volume by 50%. Lower energy consumption by 10%.

  Computing appraisal cost for quality last year

The following table lists all costs of quality incurred by Sam's Surf Shop last year. What was Sam's appraisal cost for quality last year?

  Presenting this to a project team

Project Management:  Develop a 5-6 slide PowerPoint presentation. Explain the nature of project management, the role of the project manager, and the 3 factors that affect the success of a project.In the "notes" section of the slide write the commenta..

  What tools do you find most helpful for managing projects

What tools do you find most helpful for managing projects? How can you use spreadsheet software, such as Microsoft Excel, within the various project management processes?

  Calculate the eoq and calculate the reorder point

Calculate the EOQ. - Calculate the reorder point. - Calculate the safety stock. - If we purchase 80 units or more, the unit purchase cost is reduced to $19. Calculate the EOQ for this quantity discount case.

  Show the project management question

What should be your competitive priorities and what capabilities do you want to develop in your own core and support processes?

  What type of a table would you like to create

You are the project manager for your organization and are reviewing the requirements for your new project. The business analyst has completed the requirements and is consulting with you on what each requirement is and why it's important to the projec..

  How would you respond to your customers demand

Imagine that you are a home builder with 20+ year track record of very successful and profitable construction. How would you respond to your customer's demand?

  Create a project using the project management tool

Create a project using the project management tool the team has selected. Update the project Management tool with the time spent on research and working with new technologies needed for the application for all the team members

  What would it take to change your mind

What would it take to change your mind? Provide three reasons why you do or do not vote and three things that would cause you to change your mind.

  Identify potential risks for project x

Discussion Board and comment on other postings. You will be graded on the quality of your postings

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd