Reference no: EM133091900
Construction Project Work Breakdown Structure
PROJECT - Remote Testing Centers DOT Construction Project
Business Reasons
• To construct a highly affordable houses for the people in ever growing metropolitan cities.
• Provide high security for the community living around with some security standards being implemented.
• Provide basic amenities within the facility such as grocery stores, clinics, parks for children.
• Providing luxurious houses for the elite as well to manage the demand for the project and make the rest of the project affordable.
• Quality is the main agenda here to complete the success of this project.
Project Objectives
• Overall, to create better housing for the public who are looking to stay in affordable places in and around the metropolitan cities.
• Acquire land from multiple parties and unite it to construct at a large scale and make the entire living costs affordable for the project and at the same time make the project likable at all scales.
• Everyone deserves to stay at decent places with affordable prices which rings along with the companies main objective.
• We also make sure to complete the project on time and make sure no one is dissatisfied with the project also make some returns for the investors in the project.
PROJECT SCOPE
• Build the apartments as per the approved government body policies and layouts.
• Construct the necessities for the society such as parks, clinics, groceries, recreations etc.
• Make sure to follow all the guidelines for the road widths, safety policies, first aid guidelines at the roads. Signals and speed breakers and road signs are properly installed within the community where the project is going on.
• Safety of the workers at the construction site at all times is the companies' responsibilities.
• Security management for the whole community after the construction also comes under the firms' responsibilities.
1. Develop framework for project
2. Complete a research summary on the construction plan.
3. Planning, brainstorming and getting required planning copy from the architect.
4. Consult with departmental reps and present the planning copy and get approvals of go-ahead.
5. Start construction of the project in phases
5. Networking/Information event for all departments
6. Develop department toolkit, templates, resources
7. Implementation and communication to stakeholder groups
8. Marketing and sales strategy finalizing
9. Opening up the bookings for the public who are interested
10. Handover of the completed apartments to the owners
11. Construction of other phases as per plan
12. Complete maintenance picture of the township/community