Release planning with priority

Assignment Help Basic Computer Science
Reference no: EM132552317

You will estimate the schedule of your project in VSO. Follow the steps below to estimate the schedule of your project:

1. Determine the cadence of your iterations.

2. Revisit each work item in your VSO backlog and estimate the level of effort that is required to implement it.

3. Determine the velocity of your team.

4. Calculate the number of iterations that are needed to complete the project.

Assume that you have only 1 SCRUM development team made of three developers. Also assume that the business owners mandated three release dates that the development team must commit to.

Your project schedule must span at least 4 sprints

Once you have estimated your project schedule in VSO, take a screenshot of it to submit for your assignment. Set up the starting dates of your iterations based on either regular work schedule or business mandated dates or both.

In addition to your screenshot, include a 750- to 1250-word (3-5 page) paper with the following:

- Summary of the relative level of effort for the items in your product backlog and your team velocity

- Explanation of your approach to completing this assignment and the decisions you made

- Summary of personal reflection and lessons learned in completing this assignment

 

Reference no: EM132552317

Questions Cloud

System restoration procedure : How much data has been modified between the last backup and the time of failure? What images are necessary to recover the workstation?
Describe the components of competitive advantage : Evaluate Carr's argument in "Does IT Matter?", Describe the components of competitive advantage; understand the tools of documentation of business processes;
Define key performance indicators : Define Key Performance Indicators? How it help companies to manage existing risks?
Operational excellence : Define the IT organizational structure and how the IT organizational structure impacts culture and change management practices.
Release planning with priority : Determine the cadence of your iterations. Determine the velocity of your team. Calculate the number of iterations that are needed to complete the project.
Challenges in globally-oriented organization : What are some of the project management challenges in a globally-oriented organization and how will these challenges be handled?
Create cross-functional and collaborative organization : You have collaborated with department heads to create a cross-functional and collaborative organization, good work.
Principled leadership and ethics : According to the authors, what has caused the erosion in trust and justice in leadership?
Describe strategic approach to competitive advantage : Describe one strategic approach to competitive advantage you have utilized or experienced in your life and explain why you think it was beneficial or not.

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Estimate the true proportion of california registered voters

Estimate the true proportion of California registered voters who preferred the cigarette tax increase by constructing a 95% confidence interval.

  Sheet and then insert ten records

By using Ms. Office Excel create two Work sheets and enter the columns below in each sheet and then insert ten records below these columns.

  Discuss definition of the class discount sale has a method

Suppose the class named Discount Sale is a derived class of a class called Sale, and suppose the class Sale has a method with the following heading.

  What is the purpose of the site

Why is the site's use of multimedia effective? Take notes, and repeat the exercise for a site with too much multimedia and one with too little.

  Case studies reflect real-life scenarios

Case studies reflect real-life scenarios. Analyzing case studies will help you to get a feel for what happens in real life business scenarios and how you

  Which three editions vista allow to join domain on network

Which three editions of Vista allow you to join a domain on a network

  Moment about the telecommunication industry

Think for a moment about the telecommunication industry today and what it was just a few years ago, where are we headed?

  Month interest on the overdue balance

One of your customers is delinquent on his accounts payable balance. You've mutually agreed to a repayment schedule of $596 per month. You will charge 1.2 % per month interest on the overdue balance.

  Design and implement a simulation of the game of volleyball

Design and implement a simulation of the game of volleyball. Normal volleyball is played like racquetball, in that a team can only score points when it is serving. Games are played to 15, but must be won by at least two points.

  Explanation about continuous monitoring

RMF also requires continuous monitoring and risk assessment instead of the previous three-year point-in-time assessment

  Discuss the systems development life cycle

Discuss the systems development life cycle as applied to project management: Initiation, Planning, Acquisition or design and development, Implementation, Operations/Maintenance, Disposition/Disposal

  Create better documents

Reflect on any Word templates you may have used and explain how you think these new templates in Word 2016 will help you edit and create better documents.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd