Reference no: EM13962943
Problem:
The Chop is the manufacturer of the store brand of hatchets and axes sold by various home hardware supply stores. Each item consists of a hickory handle produced in the local processing facility and a steel blade forged and polished in the local machine shop. These two items are then transported to an assembly area where the blade is attached to the handle and the item is packaged for shipment to destination stores. Because of its exclusive contracts with various stores, the shop can sell any amount of product it produces.
Skilled labor is required to produce the handles and the blades. Cheaper unskilled labor is used to assemble and package the final products. There is sufficient storage area of store the finished product prior to shipping. Assume all raw material is on-hand at the start of the quarter and there is no way to obtain additional raw material or to schedule additional labor hours.
The following provides data on a per item, per product basis:
|
Hatchet
|
Ax
|
Selling price to stores
|
$16.00
|
$29.50
|
Hickory required (ft/unit)
|
1.6
|
3.1
|
Steel required (lbs/unit)
|
1.8
|
4.2
|
Skilled labor required per unit produced
|
|
|
Handle production (min/unit)
|
5.0
|
2.6
|
Blade production (min/unit)
|
11.0
|
9.4
|
Unskilled labor required per unit produced
|
|
|
Assembly (min/unit)
|
4.0
|
5.5
|
Packaging (min/unit)
|
2.0
|
2.5
|
The following data summarizes important information for the next three months (the next quarter):
|
June
|
July
|
August
|
Contracted requirements
|
|
|
|
Minimum Hatchet production
|
200
|
200
|
225
|
Minimum Ax production
|
200
|
250
|
300
|
Costs
|
|
|
|
Skilled labor ($ per hour)
|
$12.00
|
$12.00
|
$12.84
|
Unskilled labor ($ per hour)
|
$7.00
|
$7.00
|
$7.35
|
Hickory ($ per linear foot)
|
$1.00
|
$1.20
|
$1.05
|
Steel ($ per pound)
|
$1.18
|
$1.06
|
$0.98
|
The following table provides and summary of the resource availability over the next three months.
|
Availability
|
Resource
|
June
|
July
|
August
|
Skilled Labor (total hours)
|
220
|
250
|
200
|
Unskilled Labor (total hours)
|
120
|
100
|
140
|
Hickory (total linear feet)
|
2000
|
2200
|
1500
|
Steel (pounds)
|
2000
|
2000
|
2000
|
Tasking:
Management needs to know the production schedule for June, July and August that maximizes profit. Given this production schedule, provide a 1) summary of resources used by month, by product and 2) profits by month, by product.
Create a five-year budget that supports entrepreneurs vision
: You'll create a 5-year budget that supports the entrepreneur's vision and strategy, as well as the needs for equipment, labor, and other start-up costs.
|
What is meant by the threshold energy in a particle reaction
: What is meant by the threshold energy in a particle reaction? If the threshold energy in a particle reaction holds, what can you say about the motion of the particles in the centre of momentum frame? What does this imply about the motion of the pa..
|
What is the inductance l of the primary of a transformer
: What is the inductance L of the primary of a transformer whose input is 220 V at 60 Hz and the current drawn is 5.8A? Assume no current in the secondary.
|
Prepare a brief memorandum for the president explaining how
: Prepare a brief memorandum for the president explaining how his revised assumptions affect the cash budget.
|
Raw material or to schedule additional labor hours
: Skilled labor is required to produce the handles and the blades. Cheaper unskilled labor is used to assemble and package the final products. There is sufficient storage area of store the finished product prior to shipping. Assume all raw material..
|
Conduct a contextual analysis of an organisation
: The size and constitution to be determined with the class facilitator, and to play the role of organisational consultants and to conduct a contextual analysis of an organisation.
|
What is the change in net working capital
: What is owners' equity for 2014 and 2015? What is the change in net working capital for 2015? In 2015, Parrothead Enterprises purchased $1,870 in new fixed assets. How much in fixed assets did Parrothead Enterprises sell
|
Linear programming problem
: Consider the following linear programming problem: A workshop of Peter's Potters makes vases and pitchers. Profit on a vase is $3.00; profit on a pitcher is $4.00. Each vase requires ½ hour of labor, each pitcher requires 1 hour of labor.
|
Prepare a schedule of expected cash collections
: If the company needs a minimum cash balance of $20,000 to start each month, can the loan be repaid as planned?Explain
|