Case study : [Line Balancing in a Manufacturing Plant]

This study concerns a former division of a major UK-based manufacturer of railway rolling stock and equipment. The plant manufactures a range of bogies, which are the supporting frames and wheel sets for rail vehicles. The company has a history of supplying the passenger train market in the UK but over a period of time low demand and increased competition had led it to enter new markets including European inner-city transport and the supply of freight bogies to Far East countries. The need to compete on a global basis led the company to re-evaluate its manufacturing facility with particular emphasis on the need to increase output, reduce lead times and increase flexibility. To meet these demands management had identified areas where substantial investment was required.

The Production Process

The facility layout is on a product-line basis with the manufacturing process consisting of six main stages of fabrication, welding, frame machining, paint, fitting and quality audit. Each stage must be completed in order before the next stage can begin. The stages are now briefly described:

Fabrication. The fabrication stage prepares the bogie frame sections from sheet steel and bought-in castings. A custom template is designed from which the parts required are cut from sheet steel to standard batch sizes. Parts not needed immediately are held in storage. Processed parts and castings are brought together to form a bogie 'kit', which is assembled on a jig and taken to the subsequent welding stage.

Welding.

A bogie subassembly is manually welded on a jig at a workstation to form a main bogie frame.

Frame machining. The main bogie frame is then transferred to a CNC [computer numerically controlled machine] center for the machining of any holes or bores needed for the fixing of subassemblies such as the braking and suspension systems. Bogies are fixed to a slave table and the machine processes the frame according to a preset operation sequence. Paint. The frame is then manually painted while being suspended from an overhead moving circular track.

Fitting. Manufactured subassemblies and bought-in components such as motors are then assembled on the bogie frame. The frames are placed on supports and are moved along a line at different stages of assembly with overhead cranes. Quality audit. Final inspection is carried out to ensure all bogies meet the required specification. It is usual that a certain amount of paint touch-up work is required at this stage due to damage caused to the paint finish during the fitting stage.

The Line Balancing Study

The focus of the study was on product layout design with the main objective being to ensure that the performance of the whole manufacturing system would meet required output levels. The output level was converted into a target cycle time (time between manufacture of products or output rate). As stated, the product layout consists of six main stages with the product passing through each stage in turn. This means that the effective cycle time for the whole system is determined by the stage with the longest cycle time. The study objective was to obtain a balanced line (all cycle times equal), which would enable a smooth parts flow through the production stages facilitating the introduction of a pull-type just-in-time (JIT) production control system.

A simulation model (Chapter 8) was used to estimate the cycle time at the main manufacturing stages. The graph (Figure 4.16) shows clearly where management effort needed to be directed to achieve the target cycle time. The quality audit stage was set at a nominal amount by management. Significant problems had occurred at this stage with the spray finish on the bogie frames being damaged during the subassembly fitting stage. This had to be rectified by a manual touch-up process, which could take longer than the original spray time. The paint area would also need to be reconfigured due to new environmental controls. Management had recognized the problems and an investment in an epoxy paint plant producing a hard-wearing finish was planned. The bogie frame machining center had previously been recognized by management as a bottleneck process. The bogie frame went through a number of preprogrammed steps on the machine and the cycle time was dependent on the capability of the machining center itself. Consequently a major part of the planned investment was a new machining center with a quoted cycle time below the target. An investigation of the fabrication processes revealed that although the cycle times were above target, the majority of this time was used for machine setup. Figure 4.17 shows the effect on cycle time of a reduction in setup time of 10% to 90%.

From Figure 4.17 it is clear that a setup reduction of 50% is required to achieve the target cycle time. A team was assembled to achieve this target and it was met by the use of magnetic tables to hold parts ready for processing. The simulation was rerun and the results (Figure 4.18) show the system achieving the required performance. It can be seen that a further reduction in fabrication setup times and a reconfiguration of the welding line would reduce the overall cycle time further, producing a more balanced line and increasing capacity utilization.

By implementing the changes outlined in the study the simulation was able to predict the following improvements in performance (Table 4.6).

In the table cycle efficiency = 100%-%idle time where %idle time = idle time per cycle/total cycle time.

These are substantial improvements in performance and meet the output targets set by management. However, the results in Figure 4.18 show that further reductions in the cycle times for the fabrication and weld stages would lead to a further increase in cycle efficiency, reflecting a more balanced line, and thus a further increase in output.

Source: Excerpt from Greasley, A. (2004) "The case for the organisational use of simulation''. Journal of Manufacturing Technology Management, Vol. 15, No. 7, pp. 560-566, Emerald Group Publishing. Reproduced with permission.

Question:

1. Identify the process type used in this organisation and explain the rationale to balance a production line of a manufacturing plant. ?

2. Explain the strategies that are used to balance a production line in this case study. ?

3. Explain alternative strategies to balance a production line in a manufacturing plant.

Reference no: EM132129350

Questions Cloud

What are gaap standards : What are GAAP standards? How do they influence tax and financial decisions? Please provide specific examples in your response.
Thinks kate mcclure and her boy friend spent most : Unfortunately most of the money never made it to the man. Do you thinks Kate McClure and her boy friend spent most of the money?
Firms to develop organisational ambidexterity capability : What may be some possible challenges for firms to develop organisational ambidexterity capability?
What collaboration method seems to be most popular today : What collaboration method seems to be the most popular today? Why? How do public relations differ from, but fit into a marketing plan?
Rationale to balance production line of manufacturing plant : Identify the process type used in this organisation and explain the rationale to balance a production line of a manufacturing plant. ?
Explain the impact on the firm : Discuss the matter of 2008 UBS Tax Evasion charges. Explain your understanding of their cause, the impact on the firm, and ways to prevent future evasion.
Student survey to determine student support : The administration of a college campus is conducting a student survey to determine student support for funding a new sports complex
How can companies use product differentiation : How can companies use product differentiation and the capacity control to manage rivalry and to increase an industry's profitability.
Discuss the role of warehousing in a logistics system : Prepare a 700- to 1,050-word paper defining warehousing and discussing its strategic role within the logistics system. Discuss the role of warehousing.

Reviews

Write a Review

Operation Management Questions & Answers

  Required for passenger to pass through security screening

All airplane passengers at the Lake City Regional Airport must pass through a security screening area before proceeding to the boarding area. The airport has three screening stations available, and the facility manager must decide how many to have op..

  The generations represented in the class

What suggestions would you make to the instructor or trainer as to how to better teach the cousre given the generations represented in the class?

  Estimate the additional amount of time needed to finish

The fifth unit of a 10 unit job took five hours to complete. The sixth unit has been worked on for two hours, but is not yet finished. Estimate the additional amount of time needed to finish the 10  unit job if the work has a 75 percent learning r..

  Understand the change in consumer buying behavior

The Chair Trade is an independent furniture store that specializes in selling Amish-style furniture and household items. Until the first of the year, its overall sales revenue was slowly increasing. How could the owner of the store rely on market int..

  According to the group development model

According to the group development model, which one of the following sets of issues need to be addressed as part of a group's authority issues?

  Develop a gross requirements plan for item

Given the product structure, master production schedule, and inventory status in Figure and assuming the requirements for each BOM item is 1: Develop a gross requirements plan for Item C

  Why has e business been more successful in the pc industry

Why has e business been more successful in the PC industry compared to the grocery industry? In the future, how valuable is e-business likely to be in the PC industry?

  What should be the order quantity if the inventory at time

What should be the order quantity if the inventory at the time of order placement is 71 packs?

  Sporting goods retailer rei is canceling black friday

Outdoor gear and sporting goods retailer REI is canceling Black Friday this year. No promotions, no hourly sales, no doorbusters, no waiting in line. In an unprecedented move for the modern-day holiday shopping season, REI's 143 stores will be closed..

  Accountability of clinical support services personnel

The emergence of service lines has substantially changed the accountability of Clinical Support Services (CSS) personnel.

  Implementation of contingency plan

You recently received word that Sunnydale’s neighboring town, Shadyville, reported an incidence rate of 10 new cases per 100,000 residents annually for cryptosporidiosis. What types of economic evaluations should Shadyville use to rationalize the dec..

  What ethical values are these laws and policies based upon

What laws or policies have resulted from the 2008 United States Subprime Mortgage Crisis, and what ethical values are these laws and/or policies based upon?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd