Reference no: EM131109160
Critical Thinking Activity
This critical thinking activity integrates project management (chapter 10) with knowledge of variation & standard deviation (chapter 3).
For your convenience, here is a link to the MS Word file that contains the same information as it appears: Critical thinking Activity for Project Management
You must manage a project with the following activity times (in days):
Activity
|
Optimistic Time
|
Most Likely Time
|
Pessimistic Time
|
Predecessor Activity
|
A
|
1
|
3
|
5
|
--
|
B
|
6
|
7
|
8
|
A
|
C
|
1
|
4
|
7
|
B
|
D
|
1
|
6
|
11
|
A
|
E
|
7
|
9
|
11
|
C
|
F
|
20
|
29
|
38
|
D
|
G
|
14
|
15
|
16
|
E
|
H
|
7
|
10
|
13
|
G, F
|
Complete the following tasks
1. Draw the project network
2. Compute the ES, EF, LS, LF, and slack for all activities
3. Identify the critical paths. There are TWO!
4. Report the expected completion time and standard deviation for each path.
5. Decide which standard deviation must be used for estimating probability of completion times. Justify your decision.
6. Use the mean and standard deviation to estimate the probability that the project can be finished within 55 days of when it is started.
7. Post a message to this week's DB and include:a) activities, duration, and standard deviation for each critical path,b)justification for your decision on which standard deviation to use (#5 above),c) your calculation and final answer to the probability question.
Powerpoint to the discussion thread and submit
: Once you have submitted your post, view two of your peers' presentations. Construct responses to your peers that state what you think that they did well and where you think that they could improve to assist them in their future presentations.
|
Show the offset of each local variable in the frame
: Assume control information requires 3 words and that f's return value is left on the stack. Be sure to show the offset of each local variable in the frame and be sure to provide for proper alignment (ints and floats on word boundaries and doubles ..
|
Write program that read a text file and prints only odd line
: Write a program that reads a text file and prints out only odd lines to the screen. Thus, lines 1, 3, 5,... only printed. Update your odd lines program (Q1) to write odd lines to the screen and write then lines to another file.
|
What infomation does bpim hold
: For this section, you will need to refer to the source of the Linux kernel, version 3.1.1. You may download the source code here (http://www.kemelorg/pub/li)uut/kemel/v3.0/finux-3.1.1.tar.bz2) ; however, you will probably prefer to navigate the code ..
|
Question regarding the critical thinking activity
: For your convenience, here is a link to the MS Word file that contains the same information as it appears: Critical thinking Activity for Project Management
|
The most superficial of presentations calls for some kind
: Even the most superficial of presentations calls for some kind of preparation. An "elevator speech," which summarizes a topic in minutes, if not seconds, calls for lightning thought and reflexive application of the rhetorical triangle, grammar, ou..
|
Find the average rate of change
: Find the average rate of change of f(x) on the interval [3,3+h]. Your answer will be an expression involving h.
|
What is the basis of its measurement
: What is service cost, and what is the basis of its measurement?
|
How must code generators for expressions be changed
: How must code generators for expressions be changed when they are translating an AST node that has more than one parent?
|