A refinery in Houston replaces all of the 3" full-open ball valves in its facility according to a very strict maintenance policy which spaces replacements fairly uniformly throughout the year. The refinery has approximately 1000 of these valves in place and safety regulations call for annual replacement. Ball valves are priced according to the schedule below. It costs $30 to place an order for valves and spare parts carrying costs are estimated at $7 per valve per year.
AMOUNT
PRICE
1 to 75
$22.50
76 to 119
20.00
120 +
18.25
What order quantity will enable the refinery to achieve the lowest total cost for the year in purchasing the 3" ball valves?
To construct an electricity generating unit, a company has to install 60 items. One team takes on an average 30 days to install one item.
Identify five key economic variables that could represent major opportunities or threats to a bank in your town or city.
In a manufacturing facility that produces laptop computers, there are three production lines that operate independently of each other. On one line, circuit boards on the way to final assembly that do not meet quality standards get "kicked"
Illustrate what is the logic in the least squares method of linear regression analysis. Overall the logic of least squares method is used to forecast the next quarterly sales of the organization.
An analyst must decide between two different forecasting techniques for weekly sales of roller blades: a linear trend equation and the naive approach.
The Minute Stop Market has one pump for gasoline, which can service 10 customers per hour (Poisson distributed). Cars arrive at the pump at a rate of 5 per hour
If businesses claim to have no extra-legal obligations, how can they claim the right to influence law and regulation?
Describe the conditions under which MRP is most appropriate. Explain how requirements in a master production schedule are translated into material requirements for lower-level items.
calculate the start and finish times for each activity and determine the minimum number of weeks for completing the project Identify slack in tghe activities not on the project critical path
What exactly is stress? What is the difference between so-called "good" stress or so-called "bad" stress? When it comes to dealing with the stress, does it make any difference whether it is good or bad stress?
Calculate the process capability index and advise if the process is at an acceptable level for an existing process defend your answer
The Briargrove Project has successfully completed multiple phases within the corporate offices. The project is prepared to move into remote offices across the organization.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd