Reference no: EM13349623
QUESTION 1
Case study
The Ministry of Health required the substitute of X-Ray machines for all the hospitals in Mauritius, because the existing ones have exhausted their life time and huge sums of money were being spent for repairs and maintenance. The Ministry also took this decision because complaints were received from patients since they had to wait for long to have X-rays.
Funds would be released by the Ministry of Finance but was not confirmed because the Ministry of Finance was waiting for some financial adjustments in order to release funds.
Though, the Ministry of Health decided to proceed with the project though the Ministry of Finance had not confirmed the availability of funds. The Ministry of Health advertised the procurement occasion and prepared the bidding documents which were sold to the bidders.
The bidding documents provided that procurement award would be made following the evaluation of bids, as soon as funds will be released in favour of the Ministry of Health.
In bidding documents, the Ministry of Health reserved the right to ask for a bid security any time during the evaluation process and made the award to the bidder submitting the cheapest bid with x-ray machines which can do the job according to the judgement of the Evaluation Committee and according to the criteria decided by the evaluators at the time of evaluation.
Five bids were received which were submitted to Bid Evaluation Committee for evaluation and recommendation. The BEC recommended the bid from „Top X-Ray Co. Ltd?; a company set up six months ago and it was the cheapest. The Ministry of Health awarded the contract to „Top X-Ray Co. Ltd.?.
Two bidders challenged the decision since they claimed that they were in business for X-Ray machines for 20 years and they were in a better position to carry out the repairs and maintenance; that is the after sales service. Tasks-
a) Recognize the problems in the case study for the purchase of X-Ray Machines.
b) Assess whether the conditions in the bidding documents are in line with good procurement practice.
c) The process for evaluation established in the bidding documents was adequate and correct. Discuss.
d) Did the bidders have merit in their test?
QUESTION 2
(a) Organize "Bidding Documents" that are used for public procurement in Mauritius.
(b) What are purposes, objectives and functions of the standard bidding documents?
QUESTION 3
Section 40 of PPA 2006 states that "a procurement contract shall be awarded to the bidder having submitted the lowest evaluated substantially responsive bid". What are the major procedures in evaluation of bids for the procurement of goods to arrive at the lowest evaluated substantially responsive bid?
QUESTION 4
(a) Describe procedure for selection of consultants based on -
i. Quality and Cost
ii. Quality alone
iii. Quality and Fixed Budget
iv. Least cost and acceptable quality
v. Direct Procurement
(c) List standard bidding documents for selection of consultants.
QUESTION 5
"The open advertised bidding method of procurement covers the dissimilar categories of procurement in the public sector".
a) Classify briefly different categories of procurement.
b) Illustrate briefly the standard bidding documents available under each category in open advertised bidding method.