A member of a project team that is implementing a new credit card payment process at a bank has direct responsibility to do all of the following EXCEPT:

be sensitive to conflicts between other team members and help resolve them.

ensure that the project has appropriate resources for the job to be completed.

help solve project problems that spill over into areas outside their expertise.

be called upon to share their expertise in credit card payment processes.

Question 2

Mike Multitask has three projects (A, B, and C) that are each four days long. Mike's supervisor suggests that he work first on project A, finish it, then work on project B until it is finished, and then on project C. Mike boldly declares, "My name isn't Multitask for nothing," so he decides to spend one day working on project A, one on B, one on C, then back to project A, and so on. There is no additional start up or shut down time required by splitting the projects this way. What is the difference in average completion time for all three projects when they are managed Mike's way when compared with his supervisor's suggestion?

There is no difference.

Mike's way is 3 days shorter.

Mike's way is 3 days longer.

Mike's way is 9 days longer.

Question 3

Slack time is routinely lost in a network:

at the point where multiple paths exit a common node.

at the point where multiple paths enter a common node.

at the point where the longest activity begins.

at the point where the shortest activity begins.

Question 4

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?

1, 9, 9

1, 5, 9

1, 1, 9

1, 5, 5

Question 5

You are responsible for managing a project with the following activities (times are given in days).

Activity      Expected Time    Immediate Predecessor(s)

A                 3                            ---

B                 6                            ---

C                 2                            ---

D                 5                             A

E                  2                            C

F                   7                            A

G                   4                         B, D, E

what is the critical path and expected completion time for this project?

A - F ; 12 days

A-D-G; 12 Days

B-G; 10 days

C, E, G; 10 days

Question 6

Assuming a beta distribution is being used, if the most pessimistic time for an activity increases by six weeks, what will happen to the expected time for that activity?


It will increase by one week.

It will decrease by one week.

It will increase by six weeks.

It will remain the same.

Question 7

If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

50 percent

95 percent

100 percent

It cannot be determined.

Question 8

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?

Less than or equal to $5,000

Greater than $5000 but less than or equal to $10,000

Greater than $10,000 but less than or equal to $15,000

Greater than $15,000

Question 9

You are given the following information about activity B:
Normal time = 9 weeks
Crash time = 5 weeks
Cost to crash per week = $2000
Crash cost = $41,000

What will it cost to complete activity B in 6 weeks?

Less than or equal to $34,000

Greater than $34,000 but less than or equal to $36,000

Greater than $36,000 but less than or equal to $38,000

Greater than $38,000

Question 10

You are given the following information about activity F:
Normal time = 16 weeks
Crash time = 10 weeks
Crash cost = $45,000
Cost to crash per week = $2,000

What is the normal cost for activity F?

Greater than or equat to $55,000

Less than $55,000 but greater than or equal to $47,000

Less than $47,000 but greater than or equal to $40,000

Less than $40,000

Reference no: EM13383164

Questions Cloud

Tasknbsp write a one page paper summarizing your : tasknbsp write a one page paper summarizing your thoughts.bob pierce a gentle man of about 50 is the president of abc
You are required to develop a social marketing plan for a : you are required to develop a social marketing plan for a social marketing problem and organisation of your choice.
Question 1which one of the following statements about : question 1which one of the following statements about lot-sizing rules is true? the periodic order quantity poq rule
Question 1 ten high-technology batteries are tested for 200 : question 1 ten high-technology batteries are tested for 200 hours each. one failed at 20 hours all others completed the
Question 1 a member of a project team that is implementing : question 1 a member of a project team that is implementing a new credit card payment process at a bank has direct
Write a report based on a management issue or potential : write a report based on a management issue or potential issue which they identify in the nominated case study on
Q1 define each of the following - pharmacokinetics - : q1 define each of the following - pharmacokinetics - pharmacodynamics - pharmacotherapeutics - toxicology q2common
Your client frank bearden owns an arkansas business that : your client frank bearden owns an arkansas business that brokers high-quality fresh fruits and vegetables to
Create a powerpoint presentation that will be communicated : create a powerpoint presentation that will be communicated to your manager and his fellow managers. as a group the

Reviews

Write a Review

Computer Networking Questions & Answers

  Networking and types of networking

This assignment explains the networking features, different kinds of networks and also how they are arranged.

  National and Global economic environment and ICICI Bank

While working in an economy, it has a separate identity but cannot operate insolently.

  Ssh or openssh server services

Write about SSH or OpenSSH server services discussion questions

  Network simulation

Network simulation on Hierarchical Network Rerouting against wormhole attacks

  Small internet works

Prepare a network simulation

  Solidify the concepts of client/server computing

One-way to solidify the concepts of client/server computing and interprocess communication is to develop the requirements for a computer game which plays "Rock, Paper, Scissors" using these techniques.

  Identify the various costs associated with the deployment

Identify the various costs associated with the deployment, operation and maintenance of a mobile-access system. Identify the benefits to the various categories of user, arising from the addition of a mobile-access facility.

  Describe how the modern view of customer service

Describe how the greater reach of telecommunication networks today affects the security of resources which an organisation provides for its employees and customers.

  Technology in improving the relationship building process

Discuss the role of Technology in improving the relationship building process Do you think that the setting of a PR department may be helpful for the ISP provider? Why?

  Remote access networks and vpns

safekeeping posture of enterprise (venture) wired and wireless LANs (WLANs), steps listed in OWASP, Securing User Services, IPV4 ip address, IPV6 address format, V4 address, VPN, Deploying Voice over IP, Remote Management of Applications and Ser..

  Dns

problems of IPV, DNS server software, TCP SYN attack, Ping of Death, Land attack, Teardrop attack, Smurf attack, Fraggle attack

  Outline the difference between an intranet and an extranet

Outline the difference between an intranet and an extranet A programmer is trying to produce an applet with the display shown in Figure 1 below such that whenever one of the checkboxes is selected the label changes to indicate correctly what has..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd