Question 1 a gantt chart represents mainlyanswer an

Assignment Help Applied Statistics
Reference no: EM13375132

Question 1

A GANTT chart represents mainly

Answer

an immediate identification of predecessor task.

a record-keeping device used in scheduling activities.

a general identifier.

the number of workers directly involved in the project.

Question 2

A PERT/CPM activity has an optimistic time estimate of 3 days, a most likely time estimate of 8 days, and a pessimistic time estimate of 10 days. The expected time (in days) of this activity is:
Answer

7.0

7.5

8.0

8.5

Question 3

A PERT/CPM activity has an optimistic time estimate of 4 days, a most likely time estimate of 6 days, and a pessimistic time estimate of 10 days. The standard deviation of this activity is:
Answer

7/6

1/3

2/3

1.0

Question 4

A list of the tasks, broken down into modules, components, and individual tasks, is called a
Answer

work breakdown structure (WBS).

PERT.

planning matrix.

critical path.

Question 5

A work breakdown structure breaks down a project into
Answer

weeks.

areas.

arcs.

modules.

Question 6

Consider the following project.

 

What is the critical path?
Answer

ACFG

ADFG

BEG

ACDFG

Question 7

Consider the following project.

 

What is the minimum possible time for completing this project?
Answer

15 days

16 days

18 days

20 days

Question 8

Consider the following project.

Compute the slack time for activity C.
Answer

0

4

2

3

Question 9

Consider the following project.

What is the latest possible time that Activity E can be started without delaying the completion of the project?
Answer

8

3

7

9

Question 10

Consider the following project.

What is the latest time that activity B can start without delaying the project?
Answer

0

8

4

7

Question 11

Consider the following project.

What is the latest time that activity B can finish without delaying any other activities?
Answer

0

8

9

4

Question 12

Consider the following project.

Determine the critical path.
Answer

ACEH

BCEH

BDFH

BDGH

Question 13

Consider the following project.

Determine the estimated completion time of the project.
Answer

23 days

22 days

25 days

20 days

Question 14

Consider the following project.

 

Determine the slack for activity D.
Answer

2 days

4 days

6 days

5 days

Question 15

Consider the following project.

Determine the slack for activity F.
Answer

2 days

3 days

4 days

5 days

Question 16

Consider the following project.

How much can activity F be delayed without delaying the project completion?
Answer

1 day

2 days

3 days

4 days

Question 17

Elements of project planning include
Answer

defining project objectives.

identifying activities to crash.

calculating expected times and standard deviations.

conducting a "lessons learned" session.

Question 18

If an activity cannot be delayed without affecting the entire project, then it is a ________ activity.
Answer

completed

critical

crashed

normal

Question 19

If t is the expected completion time for a given activity, then:
Answer

LF = LS - t

EF = ES - t

EF = ES + t

EF = LS - t

Question 20

In a CPM/PERT network the critical path is the
Answer

lowest path through the network.

highest path through the network.

shortest path through the network.

longest path through the network.

Question 21

Joe used a project management software package and has determined the following results for a given project:

What is the probability of completing the project within 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 22

Joe used a project management software package and has determined the following results for a given project.:

What is the probability of completing the project over 20 days?
Answer

0.3849

0.8849

0.1151

0.7642

Question 23


Once a project is underway, the project manager is responsible for the
Answer

people.

cost.

time.

All of these

Question 24


Project control involves
Answer

crashing.

three time estimates.

a backward or forward pass.

earned value analysis.

Question 25

Project management differs from management of more traditional day-to-day activities because
Answer

it has limited time frame.

it has an unlimited budget.

it is more expensive.

it involves more of the workforce.

Question 26

The LS and LF are calculated using the
Answer

backward pass through the network.

forward pass through the network.

values for ES and EF.

backward and forward pass through the network.

Question 27


The activities that must be completed prior to the start of an activity in question are called the immediate ________ of the activity in question.
Answer

successors

predecessors

successors and predecessors

followers

Question 28

The critical path is the ________ path through the network.
Answer

longest

shortest

straightest

most expensive

Question 29


The normal cost for an activity is $7,000 and the crash cost is $12,000. The normal time to complete this activity is 8 days and crash time is 4 days. If this activity is crashed by 2 days it will cost an additional:
Answer

$1000

$1250

$2000

$2500

Question 30


Which of these statements regarding project crashing is true?
Answer

Crashing is not possible unless there are multiple critical paths.

Activities not on the critical path cannot become critical after crashing.

Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.

Crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.

Save and Submit

Click Save and Submit to save and submit. Click Save All Answers to save all answers. Click Close Window to close window.

Reference no: EM13375132

Questions Cloud

Complete the following tasks and formats 1 open the final : complete the following tasks and formats 1. open the final assignment data file and save the workbook as final
Describe the structure and operations of the foreign : describe the structure and operations of the foreign exchange markets and discuss common techniques used to manage
Question no1consider a scenario of post mailbox there are : question no.1consider a scenario of post mailbox there are two processes named sender s and receiver r. both processes
I firms often face the problem of allocating an input in : i firms often face the problem of allocating an input in fixed supply among different products. nbspfind the optimal
Question 1 a gantt chart represents mainlyanswer an : question 1 a gantt chart represents mainlyanswer an immediate identification of predecessor task. a record-keeping
1 complete the following tables using hexadecimalnbsp : 1. complete the following tables using hexadecimalnbsp numbers only
Define scarcity and opportunity cost what role these two : define scarcity and opportunity cost. what role these two concepts play in the making of business decisions?a what is
Natural gas spot and future pricesthe law of one price : natural gas spot and future pricesthe law of one price implies that the spot price and the future price of a commodity
Unit 2 individual projectyou have just been asked to teach : unit 2 individual projectyou have just been asked to teach the concept of adaptation to a psychology class. you decide

Reviews

Write a Review

Applied Statistics Questions & Answers

  Find the mean, variance and standard deviation

Find the mean, median, mode, variance and standard deviation for the following nine data values and find the four quartiles and the 20 th and 80 th percentiles for the above data.

  Calculate the mean and standard deviation

Calculate the mean and standard deviation and Based on these statistics, describe how these anthropometric data compare to the US male and Chinese female populations.

  Participants select three numbers between 0 and 9

For the daily lottery game in Illinois, participants select three numbers between 0 and 9. A number cannot be selected more than once, so a winning ticket could be, say, 307 but not 337. Purchasing one ticket allows you to select one set of num..

  Forecasting with time series analysis

Develop a sales forecast for each store for December Plot the data for each store.Use data in table.

  Estimate the model time series and cross-section

Explain what type of data you would use to estimate the model - time series, cross-section, or panel data and Identify the dependent variable and the independent variables

  Relationship between perceptions of police performance

the hypothesis that there is a relationship between perceptions of police performance and area of the city for Montgomery. What might you tell the police chief?

  Sensitivity of mammography

Determine and interpret the sensitivity of mammography.

  What is the average number of breakdowns per day

This variable represents the number of machine breakdowns during a day, based on this simulation run, what is the average number of breakdowns per day?

  Single sample hypothesis testing - z-tests

Compute the single-sample z-test to see if caffeine reduces dreamtime. Test the null hypothesis at the .05 level of significance.

  1 the test averages for 40 students are listed below use 8

1 the test averages for 40 students are listed below. use 8 classes not bins to construct a frequency distribution

  What is the overall accuracy of the test

A screening test for a newly discovered disease is being evaluated. In order to determine the effectiveness of the new test, it was administered to 900 workers; 150 of the individuals diagnosed with the disease tested positive.

  Strength of chemical in stored barrels

Can the company rely on the fact that the strength of the chemical is identical from batch to batch and from barrel to barrel and what is the mean strength of the chemical in these stored barrels? How prccisc is that estimate?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd