The Queensland Health Payroll Fiasco

There are many reasons why projects of any kind fail. Analysts point to insufficient resources, inappropriate resource allocations, poor communications, and misaligned goals among many other options as possible causes of why projects fail to come in on time or on budget. However, when the project fails because of all of those concerns (as well as many other contributing factors), the high level of disappointment is often overwhelmed by the excessive economic cost of the debacle. Such is the case with the Queensland AU Health sector digital payroll disaster.

They Just Needed an Updated Payroll System

The Queensland Health System (QHS) provides public healthcare services to Australia's Queensland province. The sector has over 65,000 workers employed in its Department of Health and its 16 Health and Hospital departments. In 2006, QHS was looking for a replacement for its then soon-to-be-obsolete payroll system, support for which was set to expire in 2008. In December 2007, the agency finally contracted with IBM Australia to design and implement a new system at a budget of AU $6.9 M, deliverable in July 2008.

Early Signs of an Impending Fiasco
From its very beginning, several factors were playing into the project's ultimately disastrous conclusion:
Insufficient Calculations of Scope and Term
The complexity of the project was immense and involved the management of over 24,000 differing combinations of wage payments and withholdings for over 80,000 workers and subcontractors. Because of the fear that the existing system was in imminent danger of immediate failure, IBM agreed to take just seven months to develop and implement an "Interim Solution" to tide the agency over until a full replacement became operational.
Within that seven months, only two weeks were set aside at the beginning of the project to scope out the "critical business requirements" needed by the agency and the digital solutions that would respond to those demands. Not surprisingly, the lack of identifiable objectives was a significant cause of the project's abject bungling.
Inexperienced "Leadership"
Despite its affiliation with a global digital leader, this was IBM Australia's first attempt at delivering a project of this size. That fact was not helpful considering that QHS was probably the most complex of the Australian agencies needing the overhaul and was perhaps not the best candidate for IBM's first go.

Additionally, the "Solution Design Authority (SDA)," the state agency with the responsibility to define and maintain the scope, architecture, and design of the new system, was "passive, perhaps lazy" about communicating its requirements for a payroll system. Before project development began, the SDA accepted IBM's "incomplete, ... unsatisfactory scope [of work] documents" as is and with no questions. The project was off to a horrible start.
Too Many Players Cluttering the Field
Management of the project became even muddier after it commenced. Numerous agencies and boards divided oversight and authority, causing significant confusion which, in the end, rendered them all "ineffective in establishing a shared understanding of stakeholder expectations in relation to the quality of project deliverables":
• The SDA (which, during this period, transformed into the Program Delivery Office (PDO) of the state's "CorpTech" IT division);
• The Queensland Health Enterprise Solution Transition (QHEST), the state's information technology management program and acting project manager (which inexplicably retitled the "Interim Solution" as the "Queensland Health Implementation of Continuity" (QHIC) - no confusion there!);
• The "Executive Steering Committee" (ESC) which included personnel from CorpTech as well as the Shared Services Agency (SSA) and the Department of Education, Training and the Arts (DETA), and
• The "Release Steering Committee" which answered to both the ESC and CorpTech and counselled its Chair regarding the development of the Interim Solution.
While there appeared to be lots of oversight of the program, Australia's Auditor-General reported that "it was not clear which Accountable Officer had responsibility for the overall governance and successful completion of the whole project."
Cut to the Chase: The Consequences of this Disastrous Project
Suffice it to say that the project rolled out with the same high level of difficulty and disaster as it had begun:
• When the payroll programming finally went live in March 2010, its estimated cost was AU $101 M and the system still wasn't working. Further, analysis of the botched-but-barely-operational system in 2013 (three years after implementation) indicated that it again wasn't performing as expected and that getting it fully functioning within the next five years (by 2018) would cost another AU $836 M, taking the total cost of the project to AU $1.2 Billion.
• The state paid additional millions of dollars pursuing investigations into the causes of the failed project, each of which identified the list of factors cited above, as well as numerous other contributors to the debacle.
• The state also sued IBM to recover some of its costs expended during the project term but lost in court and was compelled to pay IBM its costs of the suit.
• But perhaps the project's worst failure was caused by the inability of team leadership to adequately plan and test the system during the development process. Back in 2010, because of time constraints and cost overruns, it was

determined to let the system go live without testing, which resulted almost immediately in over 35,000 payroll anomalies. Thousands of workers were underpaid or didn't receive payment at all, while the system inadvertently overpaid thousands of other employees by a total of AU $400 M. Queensland has consequently spent millions more collecting those unearned funds from their employees; as of July 2017, almost 32,000 QH workers still owed the state $38 M in payroll overpayment attributable to the failure of the QHS Payroll Project.
Project managers in any sector will do well to delve a little deeper into facts that drove the QHS payroll fiasco, which is an excellent opportunity to embrace the adage that it's not necessary to experience a failure to learn from one.

Question 1
This case identifies that Queensland Health System (QHS) needed a replacement for its then soon-to-be-obsolete payroll system. The issue was that support for the existing payroll system was set to expire in 2008.

Considering this case, compare the benefits of financial and non-financial project selection approaches. Provide a recommendation as to what project selection approach you would recommend and why? You need to be critical, use relevant theory, reflect on the case, and provide examples to support your answer. Use APA referencing as required.

Question 2
This case discusses a range of risks that have occurred throughout the project lifecycle. The risk project lifecycle (below), illustrates the concept that the chance of a risk occurring is more likely in the defining stage, but the cost is low. The chances of a risk occurring decreases through the project lifecycle but the cost to fix a risk event increases.

Considering the risk project lifecycle illustrated above, explain how project risks affected the Queensland Health Payroll project through its lifecycle and what the cost implications were. You should describe the risks, critically analyse what actions were taken, and recommend what actions could have been taken to mitigate those risks. You need to be critical, use relevant theory, reflect on the case, and provide examples to support your answer. Use APA referencing as required.

Question 3
This case identifies a key issue as being disorganised project leadership. This sentiment was expressed by Australia's Auditor-General who reported that "it was not clear which Accountable Officer had responsibility for the overall governance and successful completion of the whole project."

This case indicates the importance of project managers having appropriate skills. Discuss what skills are needed to be an effective project manager and explain how these skills can address the project leadership concerns. You need to be critical, use relevant theory, reflect on the case, and provide examples to support your answer. Use APA referencing as required.

Question 4
This case raises the importance of lessons learnt as a key aspect of project closure. The case concludes with the statement: "Project managers in any sector will do well to delve a little deeper into facts that drove the QHS payroll fiasco, which is an excellent opportunity to embrace the adage that it's not necessary to experience a failure to learn from one".

Considering this case, what are some of the lessons learnt that you can identify, explain why are they important for future projects. You need to be critical, use relevant theory, reflect on the case and provide examples to support your answer. Use APA referencing as required.

Attachment:- Project Management.rar

Reference no: EM133014473

Questions Cloud

Why are ppps the most common type of dmo structure : What are the weaknesses of this structure? What is the most common method of DMO funding?
Calculate the basic eps for abc ltd for the year ending : As of 30 June 2022, there were 9.75 million ordinary shares on issue. Calculate the basic EPS for ABC Ltd for the year ending 30 June 2023
Essay for business issue of coca cola company : Article Review 2 of Writing a two page essay for business issue of Coca Cola Company name: Coca Cola
Research happening today that will change the future : Research happening today that will change the future - Entrepreneurs see customer needs that others ignore and identify innovative solutions before others
Queensland health payroll fiasco : Compare the benefits of financial and non-financial project selection approaches. Provide a recommendation as to what project selection approach you would
Determine the final balance in each account balance : Paid $6,730 on August 31 for five months' rent in advance. Post the above journal entries to T accounts and determine the final balance in each account balance
Estimate the total cash outflow when project starts : The company is considering an investment into a brand new and more efficient machinery. Estimate the total cash outflow when project starts
What the amount of stock that should be measured : On 1/5/2017 the company issues $750000 of 3% loan stock at $800000 with issue cost $100675. What the amount of stock that should be measured
What is the value of the stock : A preferred stock from ABC pays $3.55 in annual dividends. If the required return on the preferred stock is 6.7 percent, what is the value of the stock

Reviews

Write a Review

Project Management Questions & Answers

  Predicting project durationyou have signed a contract to

predicting project durationyou have signed a contract to build a garage for the simpsons. you will receive a 500 bonus

  Discuss global logistics for car manufacturer

Discuss global logistics for a car manufacturer in the U.S. who outsources the manufacture of car seats to a company located in India;

  Design and write a project plan for a well-known

design and write a project plan for a well-known corporation.in an effort to learn more about initiating projects

  Control schedule and control cost processes

Issues to be covered are: The need within your organization; Your idea for control schedule and control cost processes to be implemented.

  Describing the expectancy theory

As far as describing the Expectancy Theory and give examples of its use in project management.

  What are the factors that will influence the design

PPMP20009 - Implementing lean project management to build your dream home - What are the factors that will influence the design and layout of your dream home

  Minimizing shipping expenses

The 3-blood banks in Franklin County are coordinated by a central office that facilitates blood delivery to 4-hospitals in the region. The cost to ship a standard container of blood from each bank to each hospital is demonstrate in the table given be..

  Explain the project management techniques employed

Explain the Project Management Techniques Employed. Include appropriate reports from your final project plans to corroborate your overall report.

  What would the company think about some new employee

Network Project Management - Individual case study assignment - identify and assess risk in designing, executing a major project

  What is the mean cost of your engineering effort

Using this information and a wonderful tool you mastered, Crystal Ball (CB), what is the mean cost of your engineering effort?

  Explain and sells the business idea

Idea Selection and Business Pitch - Explain and sells the business idea to potential investors and customers - Cash flow projections for the first two years

  Risk management important aspect of project management

Why is risk management an important aspect of project management?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd