Quantitative analysisnetworks pert critical path

Assignment Help Project Management
Reference no: EM13363279

Quantitative analysis:Networks, PERT, critical path. help

Company X has been told to install some new equipment. The company has 16 weeks to install the equipment. Using the following information:

IMMEDIATE ACTIVITY TIMES
ACTIVITY PREDECESSORS a m b

A --- 1 2 3
B --- 2 3 4
C A 1 2 3
D B 2 4 6
E C 1 4 7
F C 1 2 9
G D, E 3 4 11
H F, G 1 2 3

1.) What is the Critical Path?

2.) What is the expected completion time?

3.) Which activities have slack time and what are their respected slack times?

4.) What is the probability that the project can be completed in 16 weeks? (Show Work)

Reference no: EM13363279

Questions Cloud

1what percentage of the total project effort do you think : 1.what percentage of the total project effort do you think should be devoted to planning? why?2. explain the process of
Work breakdown structure wbs is one of the most important : work breakdown structure wbs is one of the most important tools in project management. understanding the project at a
Project management1 explain how does the type of project : project management1. explain how does the type of project organization affect each of the types of conflicts that occur
Purpose of a project manager1 in your own words what is the : purpose of a project manager?1 in your own words what is the purpose of a project manager pm?2 why are projects manager
Quantitative analysisnetworks pert critical path : quantitative analysisnetworks pert critical path. helpcompany x has been told to install some new equipment. the
Aspects of project management and the most time consumingin : aspects of project management and the most time consumingin your organization what aspects of the change management
How project managers can control projectslist and describe : how project managers can control projectslist and describe the different levers that project managers use to exert
Can you help me get started on thisassume that you are a : can you help me get started on this??assume that you are a consultant and you are advising an organization. they are
Network diagram and identify all the pathgiven the : network diagram and identify all the pathgiven the information in the following tableactivity duration predecessora 4

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd