Provide the mrp tables for all the finished products

Assignment Help Operation Management
Reference no: EM1377856

Q. 1. Launch the POM software also from the main menu choose Module-> Materials Resource Planning

2. Program the MRP for the problem below also solve it with the use of POM.

3. The marketing department is estimating product A's demand to be 60 units for week 4 also 50 units for week 6. There is a scheduled receipt of 75 units for component D at the beginning of week 2. Various other MRP related information for the finished products also the components are provided below.

A C D E
On hand 12 170 9 5
Lead Time 2 2 1 1
Lot Size LFL 150+ multiples of 40 multiples of 22

4. Provide the MRP tables for all the finished products also the components for the next 6 weeks.

Reference no: EM1377856

Questions Cloud

Recommends for additional protections : How common is it for an individual to be wrongfully convicted in our criminal justice system and does the criminal justice system have adequate safty in place minimizing the risk that innocent people could get put behind bars or even executed?
Explain how is model validation done : Discuss the role of modelling in research in managerial decisions making with an appropriate illustration. Explain how is model validation done.
Illustrate what volume does the equipment choice change : The variable cost would decrease $0.25 per unit. Volume for the new also improved product should rise to 50,000 units. Should the organization invest in the new equipment. At illustrate what volume does the equipment choice change.
Dynamic relationship among the speaker : The ability to understand the attributes of both the presenter and the audience is critical to a presentation. The objective and the target spectators are so closely intertwined that you should consider them coexisting variables.
Provide the mrp tables for all the finished products : Provide the MRP tables for all the finished products also the components for the next 6 weeks.
Analyzing skill sets : A recent  Opinion poll  conducted through an outside research company for my employer revealed that workers view the following skill sets as being most desirable.
Determine normal time for the task : In an attempt to raise productivity and decrease costs, Pho Shigma Company is considering to install an incentive pay plan in its producing plant.
Group interaction and development theory : Set-up a report identifying a specific theory of group interaction and development. Use this theory to the work environment. The report must cover the given topics,
Explain how decisions concerning span of management : Explain how decisions concerning span of management, the use of committees also coordination techniques affect organizational structure.

Reviews

Write a Review

Operation Management Questions & Answers

  . how does mode of transportation change

There is no word count. How does mode of transportation change when market place becomes global rather than just domestic. Is there any difference? Please give an example.

  Operations versus supply chain management

This solution discussed the similarities and differences between operations and supply chain management. You have been asked to develop a short presentation on comparing and contrasting operations management to supply chain management.

  Explain how do they differ from law enforcement and private

Illustrate what are other non-law enforcement organizations that we look to for protection? Explain how do they also "protect and serve" and explain how do they differ from law enforcement AND private security.

  Formulate an lp whose solution will enable post office

Each employee is paid $50 a day for each of first five days worked during a week also $62 for overtime day (if any). Formulate an LP whose solution will enable post office to minimize cost of meeting its weekly work requirements.

  Estimate the time it takes you to perform which operation

Now measure the time it takes while working at a standard pace. Is your estimate within plus or minus 20 percent of the estimated time.

  Research methods-root causes and research instruments

Determining potential methods of researching the issues, identifying the root causes of the issues, and determining the appropriate research instruments to collect data are all discussed. Examples are provided with the explanations.

  Illustrate what was the poka-yoke shin go created

The existing method involved assembles taking individual springs from a box containing several hundred also then placing two of them behind an ON button also two more behind an OFF button. Illustrate what was the poka-yoke shin go created.

  Illustrate what are cost also schedule variances also csi

A software development project at day 70 exhibits an actual cost of $78,000 also a scheduled cost of $84,000. Software manager estimates a value completed of $81,000. Illustrate what are cost also schedule variances also CSI. Estimate time varianc..

  Linear programming-transshipment model

RVW (Restored Volkswagens) buys 15 used VW's at each of two car auctions each week held at different locations. Formulate this problem as a transshipment linear programming model. Solve the problem using the computer. Provide a Excel file.

  Evaluate demand probability

The meat is purchased on Monday at $2.00 per pound also the shop sells the steak for $3.00 per pound. Any steak left over at the end of the week is sold to a local zoo for $0.50 per pound.

  Elucidate the principles of change management

Present at least 3 data collection methods for organizational diagnosis. Discuss Elucidate how data collecting is used in the opening stages of a change process.

  Determine upper and lower control limits

Machine's output is known to be approximately Normal with mean of 2.0 litter and standard deviation of 0.01 litter. Output is monitored using means of samples of 5observations. Determine upper and lower control limits that will include roughly 95...

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd