Question 1
Frank's machine shop operates 250 days per year. Frank sells 5,000 units per year of his most popular item, a specialty gear. The set-up cost for this gear is £100 and the monthly unit cost of holding inventory is 1% of the production cost per unit, which is £50. The lead time is 10 days. When the gear is being produced, the shop can make 80 gears per day (Hint: You should use the production model for inventory management.).
Complete the following:
1. How many gears should be produced in each run and at what minimum cost?
2. What is the cycle time?
3. Find the reorder point.
4. Draw a graph to depict inventory level against time and show on it the quantities found above. Also, what is the maximum inventory level?
Question 2
For this part of the Individual Project, you need to use the POM-QM for Windows software:
1. Read Appendix IV of the Operations Management (Heizer & Render, 2011) textbook.
2. Launch the POM-QM for Windows software and from the main menu select Module, and then Materials Resource Planning.
3. Program the MRP for the Individual Project Problem below and solve it with the use of POM-QM for Windows.
The product structure tree for the finished product A is given below.
The marketing department is estimating product A's demand to be 60 units for week 4 and 50 units for week 6. There is a scheduled receipt of 75 units for component D at the beginning of week 2. Various other MRP related information for the finished products and the components are provided below.
|
A
|
C
|
D
|
E
|
On hand
|
12
|
170
|
9
|
5
|
Lead time
|
2
|
2
|
1
|
1
|
Lot size
|
LFL
|
150+
|
multiples of 40
|
multiples of 22
|
Provide the MRP tables for all the finished products and the components for the next six weeks.
Describe and explain oracle date and time format in details
: Describe and explain Oracle Date and Time Format in details. Provide some Functions used for Date and Time and give some syntax example of their usage. Expand your examples to include some Arithmetic used with Oracle Date.
|
What is the value of bonds
: What is the value of these bonds when the required interest rate is 5 percent, 10 percent, and 15 perrcent and why is the price of Bond L more sensitive to interest rate changes than the price of Bond S?
|
What is the change in the angular velocity of the rod
: A thin rod has a length of 0.684 m and rotates in a circle on a frictionless tabletop. The axis is perpendicular to the length of the rod at one of its ends. what is the change in the angular velocity of the rod
|
Find the pitch of a roof
: Find the pitch of a roof that has a 48 foot span, if the rafters upon which the roofing will be laid are 30 feet long, including a 4 foot overhang. Suppose that the entire roofline measures 100 feet from end to end.
|
Provide the mrp tables for all the finished products
: Provide the MRP tables for all the finished products and the components for the next six weeks and draw a graph to depict inventory level against time and show on it the quantities found above. Also, what is the maximum inventory level?
|
Requirements of a unit record system
: One way of assembling information necessary to treat a patient can be found in a unit record system. What are the requirements of a unit record system, what a unit record would include, and how the information is arranged.
|
What is the change in momentum of the ball during the hit
: A tennis ball of mass 57 g is traveling in the + x direction with a speed of 38 m/s. What is the change in momentum of the ball during the hit
|
What is the ratio of your true weight vs apparent weight
: on a ferris wheel with a 15 m radius, going one loop every 7 seconds, what is the acceleration? What is the ratio of your true weight vs apparent weight
|
What is the tangential acceleration of a point on the disk
: A compact disk player has just been turned off. A disk decelerates uniformly from an initial angular velocity of 8.30 rev/s. What is the tangential acceleration of a point on the disk 3.60 cm from the axis
|