Protection design of a remote area microgrid

Assignment Help Other Engineering
Reference no: EM132130491

LOAD, FAULT LEVEL ANALYSIS & PROTECTION DESIGN OF A REMOTE AREA MICROGRID

Assignment

Please undertake the following analyses:

1. Calculate the 3-phase fault levels on Bus 2, Bus 3 and Bus 4 with the main supply connected but DG's disconnected. Then calculate the fault levels on Bus 3 and Bus 4 with the microgrid islanded (synch switch open). To do this, assume that there is a total of (group A/B/C) 500/625/750 kW of DG output in the centre of each arm of the microgrid. Then calculate the fault levels on Bus 3 and Bus 4 with the microgrid DG's in service and the main grid also connected (parallel supply).

2. Calculate the voltage drop at Bus 3 with the main supply connected but DG's disconnected at peak loading. Assume even loading; the volt drop is then equal to (half total load at the end of the line) * (line impedance). Then calculate the voltage drop at Bus3 and Bus 4 with the microgrid islanded, again at peak loading times. Although microgrid loads and DG's are evenly spread around the whole microgrid ring, for the purposes of modelling assume that the total microgrid peak load of (group A/B/C) 1000/1250/1500 kW is met by the DG's modelled as before as two of (group A/B/C) 500/625/750 kW sources, one in the middle of each arm of the microgrid.

3. For protection purposes, overcurrent and earth-fault relays are installed at CB's CB3, CB4 and each CB1. The overcurrent relays at each CB has a pick-up current, as reckoned in primary amps, of 200% of the peak load flowing at that point (the extra 100% is to prevent spurious tripping under peak load conditions). The single-phase to earth pickup currents can be set at 20% of the overcurrent (three-phase) setting on the corresponding overcurrent relay.

Design the overcurrent and earth fault relay settings (pick-up currents and time dial settings) at CB's CB3, CB4 and each CB1 when the feeder is supplied by the main grid only. To do the design, start at the relays at CB1 and work your way up the feeder to the relays at CB3and CB4. Overcurrent relay pick-up currents will be set at 150% of load. The CB1relay time setting will be 0.1. Then, using time grading techniques (use 0.35 sec grading margin between relays) determine the settings for firstly overcurrent and then earth fault relays at CB2, CB3, and CB4. The earth fault relay pick-up current settings will be 20% of the corresponding overcurrent relay setting. Again, start off with a CB1 relay time setting of 0.1, and use the standard inverse (SI) characteristic. You can calculate directly from the SI relay formula, or use the overcurrent relay setting spreadsheet "Ocurrent.xls" which is provided for your use (or alternatively, make you own one!).

4. Then analyse the situation in the microgrid when it is islanded. Will the overcurrent relays at each CB1 (Bus #3) detect microgrid faults when fed by the DG's only? Suggest some solutions to the problem. As one possible solution, consider back-to-back directional overcurrent and earth fault relays at each CB1 and recommend settings for the backward direction.

Attachment:- Power Systems Assignment.rar

Reference no: EM132130491

Questions Cloud

Review of currency of the organisational vision and mission : Review of the currency of the organisational vision and mission, make any necessary changes, and communicate the review process to stakeholders in order to gain
Requirements for a business to join the global compact : The "Did You Know?" sidebar on the UN Global Compact on reviewed how the UN is partnering with global businesses.
Identify all the lazy dollars in your financial life : Identify all the lazy dollars in your financial life. Identify source, amount and what action might be indicated.
Describe two problems or challenges you might encounter : Provide a description of each design and when it is appropriate to use each design. . Describe 2 problems or challenges you might encounter.
Protection design of a remote area microgrid : 300197 POWER SYSTEMS PLANNING & ECONOMICS - analyse the situation in the microgrid when it is islanded. Will the overcurrent relays at each CB1
Define the roles you play as a small business owner : Define the roles you play as a small business owner. Describe the main responsibilities of each role you've identified.
Why are they important for the investor to factor : Discuss one (or a few) of the basic concepts of capital budgeting such as independent vs. mutually exclusive, capital rationing, sunk costs, opportunity costs.
What are the benefits of this diet or treatment approach : What are the benefits of this diet or treatment approach? What are the potential drawbacks of this diet or treatment approach?
How did they affect you as an adult in your work life : Reflect on major events that have occurred in your life. Considering them, how did they affect you as an adult in your work life?

Reviews

Write a Review

Other Engineering Questions & Answers

  Find the worst-case values of the noise margins

Assuming that the inverter is in the logic-1 state 50% of the time and in the logic-0 state 50% of the time, find the average power dissipation in a typical circuit. The power supply is 5 V.

  Determine the pressure and quantity requirements

Determine the pressure and quantity requirements of these rock drills. Both stoping sections area accessed from the same main drive.

  The professional societies in engineering issues

What are the professional societies in engineering and what do they offer their members?

  What is the absolute maximum of ft

What is the absolute maximum of f(t)?Does this graph suggest that Social Security taxes will rise or will fall in the early 21st century? Explain.

  Cascade to form a new system

Two discrete-time systems T1 and T2 are connected in cascade to form a new system T as shown in figure. Prove or disprove the following statements.

  How the sampling error calculations for the posttest measure

Health Life is a leading provider of employee wellness programs to Fortune 500 companies. Its programs are designed to improve employee health.

  What is the use of hec-hms modelling

What is the use of HEC-HMS modelling in water supply system ,how we use it? what is the necessary input for the software?

  Find tplh - tphl and tp

For the inverter of Fig. with a capacitance C connected between the output and ground, let the on-resistance of PU be 2 kΩ and that of PD be 1 kΩ. If the capacitance C = 50 fF, find tPLH , tPHL, and tP.

  Calculate the percentage of eutectic alpha phase for this

A Cu- 30 w t% Ag alloy is cooled from 1100 degree C to 700 degree C. What is the weight percent of each phase (for this alloy) at 700 degree C°. Calculate the percentage of eutectic alpha phase for this alloy at 700 degree C. Specify the PR eutectic ..

  What is the corresponding prototype velocity

The maximum velocity on a 1-m-high model spillway is 2.2 m/s. If the prototype spillway has a height of 48 m, what is the corresponding prototype velocity?

  What will the maximum concentration of pesticide

CEE 357 Win 2014 HW#2: What will the maximum concentration of pesticide be in the pond, and how long after the spill will that concentration occur?

  The goals to achieve in the lab

Listthe type of equipment or components that you will be using? Where will you find these components? How will you use these components in Multisim/VHDL? Explain any adjustments required such as tolerances.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd