Nuclear energy is one of the possible alternative energy to meet the increasing energy demand in the world. Unlike coal and gas, nuclear power can be considered as clean from pollution. In this context, the UAE has increased its focus on this energy in order to comply with its vision of being a clean industrial country that sustain environment and people. As the risk manager of a project sponsored by Barakah, you are assigned the role of managing and evaluating risks that might affect the project during the execution phase. The project is scheduled to start from July 2021, it consists of power plant extension that include expanding the power plant building and installing new electrical machines to boost the produced electric power. During a brain storming session, you discovered that the current pandemic, due the COVID-19, could be a triggering event that might lead to the occurrence of several risky events. The following represents data about the project prior to the risk study:

Activity Description Immediate Predecessor Activity Time : T
(in days)


A Plant specifications study - 5
B environmental impact study A 6
C Engineering study A 8
D Demolition, remodeling, and dust control B 12
E Enter additional electrical machines and equipment B 20
F Job-site security B,C 16
G On site execution of the building extension D,E 25
H On site execution of the machinery implementation F 35
I Testing the new building with machines onboard F 20
J security control and safety monitoring G,H,I 14

Table: Power Plant Extension Project - Data

Part I: Risk Management
As the head of the project risk management team, you will perform some of the risk management steps by replying to the following questions:

Questions:
Propose four possible risk events that could be triggered by the COVID-19 pandemic and explain how they might affect the project.

For each proposed risk event, propose a risk response plan to face or overcome the risk (Note that risk response plans should be different for each risk event).

Attachment:- Individual Project.rar

Reference no: EM132759698

Questions Cloud

What are the responsibilities of community : What are the responsibilities of community and public health nurses in promoting health and decreasing illness and injury in populations.
How much overhead will be applied to a job : If factory overhead is to be applied per direct labor hour, how much overhead will be applied to a job incurring 20 hours of direct labor
What is evolutionary medicine : Writing a "business case" on evolutionary medicine. This is a short statement on the potential role of evolutionary medicine for your education.
How would you measure the efficiency of process : How would you measure the efficiency of the process? Did you observe lag times in the process? What part of the process was the fastest?
Propose four possible risk events that could be triggered : Propose four possible risk events that could be triggered by the COVID-19 pandemic and explain how they might affect the project
Conduct a critical appraisal of the peer-reviewed articles : Conduct a critical appraisal of the four peer-reviewed articles you selected by completing the Evaluation Table within the Critical Appraisal Tool Worksheet.
Propose a risk response plan to face or overcome the risk : During a brain storming session, you discovered that the current pandemic, due the COVID-19, could be a triggering event that might lead to the occurrence
Agile project management approaches : Briefly describe one or more Agile project management approaches.
Examine the clark healthy workplace inventory : You may think your current organization operates seamlessly, or you may feel it has many issues. You may experience or even observe things that give you pause.

Reviews

len2759698

1/11/2021 12:47:28 AM

Need to go through the handouts attached to solve case study attached, please focus in the highlighted parts. Please label the answer for each question as A B C D. ppt as completed sentences not paragraph don''t forget to add notes as short points for each slide.

Write a Review

Project Management Questions & Answers

  What is a project and what is not a project

What is a project? What is not a project? As the future CEO, why does this matter? Provide examples from either your professional or personal life that would be

  What volume per month is required in order to break even

A producer of pottery is considering the addition of a new plant to absorb the backlog of demand that now exists.

  PPMP20018 - Project Management Practicum Assignment

PPMP20018 - Project Management Practicum Assignment Help and Solution, 2019, T2 - CQ University, Australia - Reflective Practice Report

  Project management and change management

What is the difference between project management and change management?

  About international human resource management

Discuss the culture and socio-political background of the country you selected. Be sure to include a description of the legal and governmental systems.

  What additional services does the cvb provide

What additional services does the CVB provide? What are some of the obstacles/challenges the city may have to overcome? Based on the website does it encourage or discourage your group from visiting the destination?

  Improvement plan for a project management methodology

Your task is to consider the domains above and write an ESSAY illustrating and explaining continuous improvement plan for one case study.

  Describe a racist incident that you saw

Describe a racist incident that you saw. You may have been personally involved or witnessed the event.

  High-performing team possess

Discuss how each characteristic contributes to team performance. Please provide a link to the source for your answer.

  Velocity of a wave on this bungee cord

A bungee cord is stretched between two poles 332 meters apart and it has a mass of 728.3 grams.  If the force needed to stretch the bungee cord is 394 N, what is the velocity of a wave on this bungee cord?

  Identify the six members of the buying center

Provide an example of the three types of buying situations that the bookstore at your school might face when buying textbooks.

  What elements define a marketing plan

What elements define a marketing plan and what are the necessary strategic steps to reach the company's goal? Your response should be at least 200 words in length.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd